# Europakommissionens beslut den 13 oktober 1986 i målet B. ; and 45 OTHERS mot Förenade kungariket (nr 11958/86)

- Rubrik i HUDOC: B. ; and 45 OTHERS v. THE UNITED KINGDOM
- Slag: Europakommissionens beslut · språk: engelska · datum: 1986-10-13
- Ansökningsnummer: 11958/86
- ECLI: ECLI:CE:ECHR:1986:1013DEC001195886
- Artiklar (HUDOC): 8, 35, 35-1
- Slutsats (HUDOC): Inadmissible
- Källa: Europadomstolen (HUDOC), © ECHR-CEDH: https://hudoc.echr.coe.int/eng?i=001-616
- Ratio Lex: https://ratiolex.se/internationell-ratt/europadomstolen/001-616/

Elektronisk version. Den undertecknade texten i domstolens arkiv är den autentiska (art. 44.3 EKMR).

The European Commission of Human Rights sitting in private on  
13 October 1986, the following members being present:

MM. C.A. NØRGAARD, President  
J.A. FROWEIN  
F. ERMACORA  
E. BUSUTTIL  
G. JÖRUNDSSON  
G. TENEKIDES  
S. TRECHSEL  
B. KIERNAN  
A.S. GÖZÜBÜYÜK  
A. WEITZEL  
J.C. SOYER  
H.G. SCHERMERS  
H. DANELIUS  
G. BATLINER  
J. CAMPINOS  
Mrs G.H. THUNE  
Sir Basil HALL  
Mr. F. MARTINEZ

Mr. H.C. KRÜGER, Secretary to the Commission

Having regard to Article 25 (art. 25) of the Convention for the  
Protection of Human Rights and Fundamental Freedoms;

Having regard to the application introduced on 13 July 1985 by  
S.B. and 45 Others against the United Kingdom and registered on 20  
January 1986 under file No. 11958/86;

Having regard to the report provided for in Rule 40 of the Rules of  
Procedure of the Commission;

Having deliberated;

Decides as follows:

## THE FACTS

The application is introduced by 46 residents of Enfield, Middlesex,  
all members of the North/South Road Campaign Committee who are  
represented before the Commission by one of their number,  
Mr. S.B., a British national, resident in Enfield and  
Chairman of the North/South Road Campaign Committee.

The applicants have been campaigning since 1977 against the proposed  
construction by the Greater London Council (GLC) of the North/South  
Road, some 12 km in length, which will run from Bullsmoor Lane,  
Enfield in the north to Tottenham Hale in the south;  the purpose of  
the road is to relieve the Herford Road (A. 1010) and residential  
roads in the area of extraneous traffic and to provide proper access  
into and distribution between the industrial areas of Lea Valley.

The applicants object mainly to the northern alignment of the road  
which is planned to pass through a residental area where the  
applicants live and across the open land of Rammey Marsh, which local  
people use for recreation purposes; the applicants propose an  
alternative route which, according to them, will leave residential  
areas unaffected.

The applicants' objections were first examined at a public inquiry  
held in March 1982 in connection with the Enfield London Borough  
Council's District Plan for that Borough, wherein provision was made  
for Policy 34, i.e. "to press the GLC to expedite the planning, design  
and construction of the North/South Road".  In his report the  
Inspector recognised that the issues raised by the objectors required  
further consideration and that, taking these into account, he  
recommended that Policy 34 be deleted from the plan, without  
prejudice, however, to the Council's support for the road in  
principle.  The Council, however, decided to pursue the existing  
policy.

In July 1983 the GLC submitted applications to develop land in the  
London Boroughs of Enfield and Harringay for and in connection with  
the construction of the North/South Road, which were called in by the  
Secretary of State for the Environment under S. 35(1) of the Town and  
Country Planning Act 1971 ("the 1971 Act").

One hundred and seventy-six objections and representations to the  
planning application were registered and a Public Inquiry was called  
and held from 20 March to 26 April 1984.  The applicants participated  
in the Public Inquiry, put forward their alternative solution and  
challenged the GLC's traffic figures as out of date and taken prior to  
the opening of the London orbital motorway, the M.75. They also  
submitted that the effects of the North/South Road in north-eastern  
Enfield were played down by the GLC at the inquiry.

The Inspector in his report noted the adverse effects of the  
North/South Road on Bullsmoor Lane, Partners Lane and Enfield Lock  
area, where the applicants' homes are situated, and considered that  
"a number of properties will suffer a most serious loss of amenity,  
both visually and because of the noise and the general disturbance  
into what is at present a quiet residential area".  He also noted the  
measures proposed by the GLC in order to minimise the effects of the  
road on adjoining properties (such as double glazing) and he  
subsequently examined the applicants' alternative proposal which in  
his view would have significant environmental benefits and which was  
accepted by the GLC as technically possible.  However, he criticised  
it mainly on the ground that "it would change the character of the  
road from that of a road providing access to the industrial areas with  
a controlled amount of traffic using it, to an uncontrolled radial  
route into London which could be used as an alternative to the A.10".  
The Inspector recommended that planning permission be granted for the  
application subject to appropriate conditions to ensure that the  
detailed construction of the road and its landscaping being carried  
out in the manner outlined at the inquiries to ensure that the impact  
of the scheme on the surrounding areas is kept to a minimum.

The Secretary of State agreed with the Inspector's conclusions and  
accepted his recommendations.  The planning permissions were granted  
on 28 February 1985.

No application was made under S. 245 of the 1970 Act which provides  
that any person aggrieved by a decision of the Secretary of State who  
desires to question the validity of this decision, on grounds that the  
decision is not within the powers of the 1971 Act, or that any of the  
relevant requirements have not been complied with in relation with the  
decision, may, within six weeks from the date on which the decision is  
taken, make an application to the High Court.

The construction of the road has started, and on 9 March 1986 it was  
approaching Enfield Lock.

## COMPLAINTS

The applicants complain that their right to respect for their home,  
private and family life, as guaranteed by Article 8 (art. 8)  
of the Convention, has been infringed by the construction of the  
North/South Road.

The applicants submit that, although the North/South Road was intended  
to provide for a proper access into, and a proper distribution between  
the industrial areas of the Lea Valley, its entire northern alignment  
is planned to pass through the purely residential areas of Partners  
Lane, Bullsmoor Lane and Enfield Lock.

The applicants complain of the devastating effects, both visually and  
because of the noise, pollution and general disturbance, that the  
construction of the road will have on their homes and on the peace and  
quiet of their family lives; some families will lose parts of their  
gardens and others will be almost sealed in their houses as a result  
of the double glazing.  The environmental impact of the road will be  
disastrous for the area and its character as a peaceful, quiet  
residential area will be irreparably and definitively altered.

The applicants propose an alternative route which would satisfy the  
needs for which the North/South Road in its present form is  
constructed and still leave residential areas unaffected.  They submit  
that the technical feasibility of this alternative proposal has been  
recognised by the GLC.

## THE LAW

The applicants have complained that the construction of the  
North/South Road violates their right to respect for home and private  
and family life.  They invoke Article 8 (art. 8) of the Convention.

It is true that Article 8 (art. 8) of the Convention secures to  
everyone the right to respect for his private and family life and his  
home. However, the Commission is not required to decide whether or not  
the facts alleged by the applicant disclose any appearance of a  
violation of this provision as, under Article 26 (art. 26) of the  
Convention, it may only deal with a matter after all domestic remedies  
have been exhausted according to the generally recognised rules of  
international law.

The Commission recalls its previous decision (No. 9515/81, 7.5.82,  
D.R. 28 p. 243) where it held that the applicant failed to exhaust  
local remedies as required by Article 26 (art. 26) of the Convention  
by not pursuing his appeal against the High Court judgment dismissing  
his action to challenge under Schedule 2 para. 2 of the Highways Act  
1959 the Minister's orders made under Sections 7 and 9 of the Highways  
Act 1959 for the construction of a road.

The Commission noted that although the applicant was not able to plead  
Article 8 (art. 8) of the Convention as such before the High Court, he  
was able to submit that the road would constitute an irreparable  
nuisance, which was a submission which went to the substance of his  
complaint of an interference with his Convention rights.  Thereupon  
the Commission held that by abandoning his appeal the applicant failed  
to exhaust a remedy which would, if successful, have been effective to  
redress his complaints under United Kingdom law.

In the present case, the Minister's decisions granting applications  
for planning permission were taken under S. 35(1) of the 1971 Act.  
The Commission notes that no application was made under S. 245 of the  
1971 Act to challenge the validity of the decisions.  The Commission  
also notes that that section is in exactly the same terms as the  
remedy under Schedule 2 of the Highways Act 1959 (now 1980) which the  
applicant in Application 9515/81 failed to pursue and accordingly in  
the present case the applicants' failure to challenge under S. 245 of  
the 1971 Act the Minister's decisions granting applications for  
planning permission means that they have, therefore, not exhausted the  
remedies available to them under United Kingdom law. Moreover, an  
examination of the case does not disclose the existence of any special  
circumstances which might have absolved the applicants, according to  
the generally recognised rules of international law, from exhausting  
the domestic remedies at their disposal.

It follows that the applicants have not complied with the condition as  
to the exhaustion of domestic remedies and their application must be  
rejected under Article 27 para. 3 (art. 27-3) of the Convention.

## For these reasons, the Commission

## DECLARES THE APPLICATION INADMISSIBLE.

Secretary to the Commission               President of the Commission

## (H.C. KRÜGER)                             (C.A. NØRGAARD)