# Europadomstolens sammanfattning av avgörandet den 28 mars 2000 i målet Aldo and Jean-Baptiste Zanatta mot Frankrike (nr 38042/97)

- Rubrik i HUDOC: Aldo and Jean-Baptiste Zanatta v. France
- Slag: Sammanfattning · språk: engelska · datum: 2000-03-28
- Ansökningsnummer: 38042/97
- Artiklar (HUDOC): 6, 6-1, 41
- Slutsats (HUDOC): Violation of Art. 6-1;Pecuniary damage - claim dismissed;Non-pecuniary damage - financial award;Costs and expenses partial award - Convention proceedings
- Källa: Europadomstolen (HUDOC), © ECHR-CEDH: https://hudoc.echr.coe.int/eng?i=002-6696
- Ratio Lex: https://ratiolex.se/internationell-ratt/europadomstolen/002-6696/

Elektronisk version. Den undertecknade texten i domstolens arkiv är den autentiska (art. 44.3 EKMR).

Information Note on the Court’s case-law 16

## March 2000

## *Aldo and Jean-Baptiste Zanatta v. France* - 38042/97

Judgment 28.3.2000 [Section III]

## Article 6

## Civil proceedings

## Article 6-1

## Civil rights and obligations

Applicability of Article 6 to proceedings concerning the annulment of a prefectoral decree declaring an expropriation of property to be in the general interest: *Article 6 applicable*

## Reasonable time

Length of administrative proceedings: *violation*

*Facts*: In a prefectoral decision of 17 September 1990 the compulsory purchase by the local authority of property belonging to the applicants was declared to be in the public interest.

On 1 March 1991, after the prefect’s refusal to reconsider his decision, the applicants applied to the Besançon Administrative Court for judicial review of the decision. On 16 April 1992 the Administrative Court dismissed the applicants’ application. The application was renewed before the *Conseil d’Etat* and preparation of the case for trial began on 19 November 1992. In a judgment of 5 March 1997 the *Conseil d’Etat* dismissed the application. In the interim the civil courts had delivered a final decision on 22 December 1992 concerning the amount of compensation for the expropriation.

*Law : *Article 6 § 1: *Applicability* – While proceedings challenging the lawfulness of the expropriation order indeed related to the assessment of the public interest of the expropriation, it was the stage prior to the transfer of ownership itself, so that the outcome had a direct impact on the applicant’s right of property, a “civil” right law” nature within the meaning of the Convention. That stage had public-law aspects, but the Court reiterated that under its case-law the fact that the applicable law was based on the requirements of the general interest had no bearing. Lastly, in the Guillemin judgment, the Court had found Article 6 to be applicable in proceedings identical to those in this case. Article 6 was therefore applicable.

*Length of proceedings* – The proceedings had lasted six years. The period of inactivity in the *Conseil d’Etat* could not be justified by the conduct of the applicants.

*Conclusion*: violation (unanimously).

Article 41: The Court awarded 15,000 French francs (FRF) to each of the applicants in respect of non-pecuniary damage and FRF 5,000, likewise to each of the applicants, for costs and expenses.

© Council of Europe/European Court of Human Rights  
This summary by the Registry does not bind the Court.

Click here for the Case-Law Information Notes