# Europadomstolens sammanfattning av avgörandet den 2 september 1997 i målet Abenavoli mot Italien (nr 25587/94)

- Rubrik i HUDOC: Abenavoli v. Italy
- Slag: Sammanfattning · språk: engelska · datum: 1997-09-02
- Ansökningsnummer: 25587/94
- Artiklar (HUDOC): 6, 6-1, 41
- Slutsats (HUDOC): Violation of Art. 6-1;Pecuniary damage - claim dismissed;Non-pecuniary damage - financial award;Costs and expenses award - Convention proceedings
- Källa: Europadomstolen (HUDOC), © ECHR-CEDH: https://hudoc.echr.coe.int/eng?i=002-8888
- Ratio Lex: https://ratiolex.se/internationell-ratt/europadomstolen/002-8888/

Elektronisk version. Den undertecknade texten i domstolens arkiv är den autentiska (art. 44.3 EKMR).

Information Note on the Court’s case-law No.

## September 1997

## *Abenavoli v. Italy* - 25587/94

Judgment 2.9.1997

## Article 6

## Administrative proceedings

## Article 6-1

## Reasonable time

Length of proceedings in administrative courts: *violation*

[This summary is extracted from the Court’s official reports (Series A or Reports of Judgments and Decisions). Its formatting and structure may therefore differ from the Case-Law Information Note summaries. It also covers the following judgments of 2 September 1997 against Italy: *De Santa *(25574/94), *Nicodemo *(25839/94) and *Lapalorcia *(25586/94)]

### I. ARTICLE 6 § 1 OF THE CONVENTION (“REASONABLE TIME”)

A. Applicability

Applicants asserted either a purely economic right (*De Santa*, *Lapalorcia* and *Abenavoli*) or an essentially economic right (*Nicodemo*); administrative authorities’ discretionary powers not in issue – cases’ private-law features predominated over public‑law features.

*Conclusion*: Article 6 § 1 applicable (seven votes to two: *De Santa*, *Lapalorcia* and *Abenavoli*; six votes to three: *Nicodemo*).

B. Compliance

**1.** Periods to be taken into consideration

Starting-point (in each case): institution of proceedings in Regional Administrative Court (“the RAC”).

End: date of deposit with registry of Consiglio di Stato’s judgment (*De Santa*); date on which RAC’s judgment became final (Lapalorcia); proceedings still pending (*Abenavoli* and *Nicodemo*).

Total: from approximately six years and two months (*Lapalorcia*) to nearly seventeen years (*De* *Santa*).

**2.** Applicable criteria

Certain stages of proceedings considered in each case.

*Conclusion*: violation (seven votes to two: *De Santa*, *Lapalorcia* and *Abenavoli*; six votes to three: *Nicodemo*).

### II. ARTICLE 50 OF THE CONVENTION

A. Damage

1. Pecuniary damage: not claimed (*De Santa*); claim dismissed, for lack of causal connection with violation found (*Abenavoli* and *Nicodemo*).

2. Non-pecuniary damage: claim allowed in part (*De Santa*, *Abenavoli* and *Nicodemo*).

**3.** Pecuniary and non-pecuniary damage: claim allowed in part (*Lapalorcia*).

B. Costs and expenses

Before Court: claim allowed in part (*De Santa*) – before Convention institutions: claim allowed in part (*Lapalorcia* and *Abenavoli*) – not claimed (*Nicodemo*).

*Conclusion*: respondent State to pay applicants specified sums (unanimously: *De Santa*, *Lapalorcia* and *Abenavoli*; eight votes to one: *Nicodemo*).

© Council of Europe/European Court of Human Rights  
This summary by the Registry does not bind the Court.