Finansiering och riskdelning vid investeringar i ny kärnkraft – Chapter 9: Swedish model for financing and risk sharing

2024-08-12 · 85 sidor, varav 84 med tryckt sidnummer


Så kom texten hit

  • Källa: Regeringskansliet (regeringen.se) — originalets PDF · regeringens sida; texten är pdf:ens eget textlager
  • Textkvalitet: Märkbara fel — ungefär 0,7 % av orden ser trasiga ut; enstaka ord kan vara felavlästa
  • Sidnummer: 84 av 85 sidor bär tryckt sidnummer ur källan; övriga visas utan nummer

Varje sida nedan har en egen länk ”Kontrollera mot PDF” till originalet på just den sidan.

Citera

Promemoria Finansiering och riskdelning vid investeringar i ny kärnkraft – Chapter 9: Swedish model for financing and risk sharing (Finansdepartementet, 2024-08-12)

Dokumentets text

s. 1 Kontrollera mot PDF

9

Swedish model for financing and
risk sharing

9.1

Introduction

This chapter presents the Inquiry’s proposal for a financing and risksharing model for investing in new nuclear power. The chapter
begins in Section 9.2 with a discussion of the criteria that have
guided the choice of model. Section 9.3 provides a general
description of the model.
It is about 40 years since the last nuclear power plant was built in
Sweden. Building new reactors again in Sweden is expected to be
relatively expensive because recent experience is lacking and new
supply chains will need to be built up. Therefore, the model is
intended to finance a programme equivalent to 4 000–6 000 MWe
(megawatts electric) of installed generator capacity, corresponding
to about four large-scale reactors. Subsequently, it can be expected
that both the costs and risks associated with building new nuclear
power will have fallen, and thus also the need for state aid.
Section 9.4 describes the scope of the programme and what
conditions an application to participate in the financing and risksharing programme must meet in order to be approved.
Section 9.5 provides a detailed description of the different
components of the model: state loans, price hedging arrangements,
and a risk- and gain-sharing mechanism. The level of support a
nuclear power project receives depends on the values assigned to the
model’s parameters.
In Section 9.6 the Inquiry describes the parameters chosen,
which are deemed reasonable based on the prevailing external
conditions. If these conditions change, it may change what
parameters in the model are deemed to be appropriate and

1

s. 2 Kontrollera mot PDF

reasonable. To illustrate this, the section includes sensitivity
analyses.

9.2

Model criteria

A number of criteria have guided the Inquiry’s choice of model. An
important criterion is that the production cost for electricity should
be low. This is achieved in the model through, for example, state
loans with low interest rates, where the Swedish Government takes
all the credit risk for the loans. The cost of producing electricity
from a new reactor also depends on the capital cost of building it. It
is inevitable that a higher capital cost leads to higher production
costs for the electricity produced. This criterion should therefore be
interpreted as meaning that the model should give a low cost to
produce the electricity in relation to the capital cost.
It is also necessary for central government to share the risks
during the construction phase in order to reduce the financing cost.
The risk-sharing model must ensure that the drivers for
implementing a nuclear power project cost-effectively are strong.
The precision of incentives is therefore an important criterion for
the model. Another criterion is that the risks for public finances are
not excessive. What is an acceptable level of risk is ultimately a
political stance. A relatively large proportion of equity capital and
the precision of incentives in the risk sharing are factors that reduce
the risk of credit losses on the central government loans.
As shown in Chapter 6 Socio-economic analysis, there are market
failures that can justify state aid. The link between market failures
and forms of support cannot be made perfectly, so that one form of
support can be identified in each market failure. However, there is a
link in the Inquiry’s model between its different components and
the market failures that have been identified.
The Swedish Government has a planning objective for electricity
production of 300 TWh by 2045. It is not certain whether such an
objective can be achieved solely with renewable electricity, and
whether such a weather-dependent electricity system can be
balanced at a reasonable cost. State aid to nuclear power can
therefore also be justified because it can be cost-effective in relation
to the planning objective.

2

s. 3 Kontrollera mot PDF

One criterion is that the financing and risk-sharing model can be
assessed as able to pass a state aid investigation. A further criterion
of crucial importance for the design and application of the model is
that the project’s expected return is high enough that private actors
are willing to finance new nuclear power. If the cost of building new
nuclear power is very high, the required return of the owners may be
incompatible with an acceptable risk to public finances and with a
reasonable cost for producing electricity. However, the Inquiry
assesses that the conditions are good for the proposed financing and
risk-sharing model to enable new nuclear reactors to be built with
acceptable risks to public finances and at a reasonable cost for
electricity production, and where reasonable return requirements
can be met.

9.3

General description of the model

9.3.1

The three components of the model

The financing and risk-sharing model has three components that
operate to reduce the cost of capital and enable investments in
nuclear power at a low cost.
State loans (section 9.5.1)
State loans are issued by the National Debt Office to finance
investments in new nuclear power, which lowers the cost of capital.
State loans enable a capital structure with a higher proportion of
debt capital during the construction phase than can be obtained on
market terms, and at a lower interest rate than the market rate. Once
the nuclear power plant enters the operational phase, the uncertainty
surrounding the project decreases, which enables market financing
on significantly better terms than during the construction phase.
The interest rate on the state loans is gradually raised during the
operational phase to provide an incentive to replace the state loans
with financing from the market.

3

s. 4 Kontrollera mot PDF

Price hedging arrangements (Section 9.5.2)
A price hedging arrangement of the two-way contract for difference
(CfD) type is signed between central government and the nuclear
power generator. The CfD is designed to preserve market-based
incentives as far as possible. For periods when the market price of
electricity is lower than the agreed strike price, a cost arises for
central government that is financed by a tax proportional to
electricity consumption, paid by all electricity customers. Where the
market price is higher than the strike price, central government will
receive income from the contract for difference which can be passed
on to the electricity consumer.
Risk- and earnings-sharing (Section 9.5.3)
The third component is a risk- and earnings-sharing mechanism that
gives the project owners a minimum return on their investment.
Beyond this, in the best outcomes, earnings from the project are
shared between central government and the electricity consumers.
The mechanism is activated based on the results of a market
valuation of the project after the nuclear power plant has come
online. If the return in the project turns out to be significantly better
or worse than expected, the terms and conditions regulating the
state loans and the CfD are adjusted accordingly. A floor and ceiling
for the return on equity during the construction phase determines
whether the terms and conditions should be made more favourable
or tightened up. The risk- and gain-sharing mechanism remains
active until the value of the equity in the project has been restored
to lie between the floor and ceiling. After this, the project stands on
its own with the expectation of a market rate of return.
9.3.2

How risk is managed in the model

The previous chapter identified four main categories of risk that are
considered to have a significant impact on the returns by investors
and are therefore particularly important to manage with a view to
reducing the overall project cost (figure 9.1figure 9.1).

4

s. 5 Kontrollera mot PDF

Figure 9.1

Important risks in the four phases of a nuclear power project

Note: FID: Final Investment Decision, COD: Commercial Operation Date, EoL: End of Life.

Construction risk
In light of the cost overruns and delays that have occurred in recent
European nuclear power projects, interest from private investors is
limited prior to commissioning. Although there are examples of
projects financed with private capital where the investor bears the
construction risk, the risk premium is significant, leading to a high
cost for producing nuclear electric power.1 The proposed financing
and risk-sharing model manages construction risk in two main ways.
State loans enable project financing on better terms than the
market can offer at the time of the investment. This provides
investors with guaranteed low-cost debt financing during the
construction phase, even in the event of cost overruns and delays.
In addition to the state loans, there is the risk- and gain-sharing
mechanism, which more directly limits the exposure for investors
during the construction period. The investor receives a low but
positive return in all but the most extreme cost overrun scenarios,
while the incentives to run the project as efficiently as possible in
order to achieve a better return than that provided by the lower
threshold value are preserved. Compared to other countries’ risksharing models – which remunerate cost overruns that fulfil predefined contractual terms or after assessments by a regulatory
1

In the UK Hinkley Point C project, the project owner bears the construction risk but gets a
strike price that at the current price level exceeds 150 öre/kWh.

5

s. 6 Kontrollera mot PDF

authority – the proposed model’s approach is assessed as providing
more comprehensive support.
Market risk
In the present context, the term ‘market risk’ refers to uncertainty
about the future demand for electricity and the price at which it can
be sold. According to the socio-economic analysis (see Chapter 6),
there is no well-functioning market for hedging arrangements with
the durations required for a nuclear power project.
By entering into a price hedging arrangement with the generator,
central government gives investors certainty about future revenue
from nuclear electric power. The contract design proposed by the
Inquiry means that the remuneration from the CfD is decoupled
somewhat from the amount of electricity actually produced. This
provides investors with predictable revenue while preserving market
incentives. Overall, the CfD provides coverage for a significant
portion of the market risk over a long period.
Political and regulatory risks
Political and regulatory risks affect a nuclear power project
throughout its life cycle. During the construction phase, there is
uncertainty about the interpretation of building standards and safety
requirements, which are also at risk of changing during the project.
In the operational phase, there is uncertainty about, for example,
future charges and taxes that could affect the profitability of the
project. When it comes to decommissioning and the final storage of
radioactive waste, new requirements and more extensive review
procedures than anticipated may result in increased costs and delays.
Finally, there are more unlikely scenarios where energy policy
decisions are made that severely restrict or completely prohibit
nuclear activities.
No financing and risk-sharing model can manage all political and
regulatory uncertainties that may arise in a nuclear power project
spanning over 100 years. However, the three components of the
proposed model work together to significantly reduce these
uncertainties.

6

s. 7 Kontrollera mot PDF

Central government entering into private law contracts with the
project owners (loan agreements and hedging arrangements/CfDs)
provides a clear basis for central government’s undertakings and
grounds for demanding financial compensation in the event of
breach of any of the contractual terms and conditions. This reduces
the likelihood of policy decisions having a negative impact on the
profitability of nuclear power. Furthermore, the risk- and gainsharing component mitigates the consequences of regulatory
changes. The lower threshold value of the risk-sharing mechanism
provides a minimum return on equity until commissioning and
means that the investor is somewhat protected for instance against
cost increases resulting from changes in safety requirements during
the construction phase.
The proposed model does not include an investor remuneration
scheme agreement, similar to that used in, for example, the Czech
Republic and the UK, to share responsibility for cost increases
resulting from political decisions and changes in regulatory
frameworks. The Inquiry’s assessment is that it is challenging to
identify, contract on, and in practice determine which cost overruns
are to be financed by the project owner, central government or the
electricity consumers. However, it cannot be ruled out that further
measures to limit political and regulatory risks may become
necessary.
Programme risk
Programme risk refers to the risk that the profitability of a project
will deteriorate as a result of not building enough nuclear power
plants to realise vital economies of scale. Programme risks exist in
all phases of a nuclear power project, but especially in the
decommissioning phase. Uncertainty about opportunities to realise
economies of scale that are linked to the costs of decommissioning
and the final storage of nuclear waste products in particular can
negatively affect willingness to invest. The disposal of nuclear waste
involves a complex licence application procedure as well as the
construction of facilities and systems for transport, interim storage
and final storage. This entails major capital investments in fixed
assets but a relatively low marginal cost for additional waste once

7

s. 8 Kontrollera mot PDF

they are in place. From the perspective of the individual project
owner, the risk is that not enough reactors are built to provide the
economies of scale needed to achieve profitability in nuclear waste
repository projects.
Sweden currently has a well-functioning system for the financing
of nuclear waste product handling and final storage based on the
polluter pays principle. The current Swedish nuclear power
generators are individually responsible for financing the
management of their nuclear waste, but in practice coordinate this
task through a jointly owned company Svensk Kärnbränslehantering
(SKB). However, the existing and planned repository facilities are
fully encumbered for the storage of the waste from existing reactors.
In addition, it is planned to extend the reactors’ lives, which will
result in more nuclear fuel being spent and requiring final storage.
In addition, there is no guarantee that any new players will be able
to utilise SKB’s existing repositories concept.
Issues related to the financing of nuclear waste from new reactors
are being investigated within the framework of the Nuclear Power
Procedures Inquiry (KN 2023:04) and through government
assignments to the Swedish National Debt Office
(KN 2024/01243). This Inquiry considers it inappropriate to
anticipate the results of that inquiry and those assignments.
What the present Inquiry can contribute to limit the programme
risk is to propose a financing and risk-sharing model that is
sufficiently large to provide the necessary economies of scale,
provided that the programme is fully subscribed.2

9.4

Size of the programme, etc.

9.4.1

Size of the programme

Proposal: The financing and risk-sharing model should cover
investments in new nuclear power corresponding to installed
capacity of 4 000 to 6 000 MWe. All projects within the
programme should be subject to the same terms and conditions.

2

Vattenfall (2024) estimates that the size of a new nuclear power programme needs to be at
least 3–4 GW to make ends meet in a new repository for nuclear waste.

8

s. 9 Kontrollera mot PDF

Reasons behind the proposal
According to the Inquiry’s terms of reference, the financing and
risk-sharing model should be designed in such a way that nuclear
power with a total output of at least 2 500 MWe is in place by 2035.
However, as discussed in previous sections, 2 500 MWe is not
considered sufficient to realise the economies of scale necessary for
investments in the individual projects to be profitable. In particular,
investments in new repositories for nuclear waste require a larger
volume of electricity produced over which the fixed costs can be
distributed. The Inquiry therefore makes the assessment that the
size of the programme should be 4 000–6 000 MWe of installed
generator capacity, corresponding to around four large-scale
reactors.
The first of these new reactors built in Sweden will probably be
more expensive than its successors. This could justify a
differentiated setting of the parameters in the model, where the first
projects would receive stronger support, such as more favourable
terms and conditions in the hedging arrangement. However, the
Inquiry assesses that in practice it will be difficult to quantify any
learning effects within the context of the first 4 000–6 000 MW of
nuclear power to be built in Sweden. Thus, in the model the Inquiry
views all projects within the programme as ‘first of a kind’ that ought
to have similar terms and conditions.
9.4.2

Regulation of the proposed programme and
examination of applications for aid

Proposal: A new act of law is introduced that regulates forms of
aid and the conditions for receiving this aid.
Under the proposed new act, if there is a reason for doing so
and following an application procedure, the Government may
decide to grant aid to companies for investments in new nuclear
power. Aid may be granted if the investment:
- covers the construction of one or more nuclear reactors with
a combined output of at least 300 MW;
- is made in an activity that, at the time of the decision to grant
aid, is covered by a licence under the Nuclear Activities Act

9

s. 10 Kontrollera mot PDF

(1984:3) and has been permitted under Chapter 17 of the
Swedish Environmental Code; and
- is made in a company that is not operating other activities
than the one that the investment covers.
In addition, aid may only be granted to a company if those
with a qualifying shareholding in that company have the capacity
to exercise responsible ownership, and if those who are members
of the company’s board of directors or management team have
the capacity to carry on the activity in a responsible way.
Aid may be granted in the form of loans and two-way CfDs,
and may only be granted in accordance with the European
Commission’s decision on the approval of aid under
Article 107(3) of the Treaty on the Functioning of the European
Union (TFEU).
An application for aid must be in writing and must include a
business plan showing the expected values of the revenues and
expenses. Expected values refers here to the weighted average of
the possible outcomes assumed for the calculation. The business
plan must also list significant risks, including how these arise, are
measured and managed. The Government or the government
agency decided by the Government may issue additional
regulations concerning what the application must contain.

Reasons behind the proposal
A new act of law should be introduced
Financial power, i.e. the right to made decisions concerning central
government revenue and expenditure, is regulated in Chapter 9 of
the Instrument of Government of Sweden. According to Chapter 9,
Art. 1, the Riksdag decides on the central government budget, but
according to Chapter 9, Art. 8, central government’s assets are in
principle at the disposal of the Government. According to
Chapter 9, Art. 7 however, appropriations and revenue may not be
used in ways not approved by the Riksdag. It therefore falls to the
Government to execute the Riksdag’s decisions. Furthermore,
without the consent of the Riksdag, the Government may not take
up loans or otherwise assume financial commitments on behalf of
central government unless authorised by the Riksdag (Chapter 9,
10

s. 11 Kontrollera mot PDF

Art. 8–9 of the Instrument of Government). Further provisions
concerning the competence and responsibilities of the Riksdag and
the Government in respect of the budget are laid down in the
Riksdag Act or in separate legislation (Chapter 9, Art. 11 of the
Instrument of Government).
The Budget Act contains general provisions on the
Government’s competence and responsibilities in relation to central
government’s budget. With separate legislation, the Riksdag may
decide on regulations that deviate from the provisions in the Budget
Act on certain matters. According to the usual principles of law,
such a separate legislation takes precedence. On the basis of the
provision on residual powers in Chapter 8, Art. 7 second paragraph
of the Instrument of Government, the Government may issue
regulations on the implementation of the central government budget
(Chapter 11, Section 2 of the Budget Act).3 In turn, on the basis of
Chapter 8, Art. 11 of the Instrument of Government, the
Government may authorise an authority under the Government or
an authority under the Riksdag to issue such regulations.
Even though they concern a relationship between individuals and
the public domain, regulations which are not burdensome but
beneficial or neutral from the point of view of the individual can
come under the Government’s residual powers.4 The powers
conferred on the Government to issue regulations in a particular
matter do not preclude the Riksdag from adopting provisions on the
same matter (Chapter 8, Art. 8 of the Instrument of Government).
The Riksdag may thus promulgate legislation within the scope of the
Government’s residual powers. This has also happened to some
extent, particularly with regard to administrative procedure and the
main social security benefits.
Concerning the issue of state aid, it can be granted in the form of
individual aid or through the introduction of an aid scheme within
which aid may be granted by a government agency, for example (see
Chapter 7). Once an aid scheme has been approved, the European
Commission need not be informed in advance of any individual aid
measures taken under the scheme, unless the Commission has
included a proviso concerning this in its decision to approve the
scheme.
3
4

See also Govt Bill 2010/11:40 p. 160.
See Govt Bill 1973:90 p. 210.

11

s. 12 Kontrollera mot PDF

Aid schemes are usually regulated at the Ordinance level and are
issued under the Government’s residual powers. Ordinances often
also specify the forms of aid, such as grants or guarantees, and the
conditions for receiving the aid in question. Since under Chapter 9,
Art. 8, second paragraph of the Instrument of Government, the
Government may not take up loans or otherwise assume financial
commitments on behalf of central government unless authorised by
the Riksdag, aid schemes are designed with this in mind. This is
usually done by allowing the government agency in question to
make decisions on state aid, provided that funds have been set aside
for the purpose in question.
In order for the Government or a government agency to be able
to assume financial commitments that tie up future appropriations,
i.e. expenditure during future budget years, an authorisation to place
orders (Chapter 6, Section 1 of the Budget Act) is required.
Furthermore, the Government may only approve lending that is
financed by loans in the National Debt Office if approval has been
obtained from the Riksdag (Chapter 6, Section 3 of the Budget Act).
This arrangement allows the annual perspective of the budget to be
maintained. The authorisation states what the funds or lending may
be used for. Directives only address the Government.
As mentioned above, the Commission’s approval for state aid can
be granted for either an aid scheme or individual aid. In the case of
nuclear power, the aid so far approved by the Commission has
concerned aid granted directly to individual companies on more or
less tailor-made conditions (see Chapter 8), where the aid was
designed in dialogue with the beneficiary and subsequently notified
to the Commission.
Although approval for state aid may require a specific project to
be notified, it cannot be ruled out that notifying an aid scheme
instead could be an option in the case of nuclear power. Since an aid
scheme targets a wider circle of potential beneficiaries, it ought to
be regulated in legislative form. Furthermore, it is proposed that the
aid should apply over a number of budget years through the
establishment of a programme, which means that any provisos and
terms and conditions that the Riksdag has announced regarding the
form of the aid must be repeated in each budget bill unless they are
specified in a separate act of law. Furthermore, the introduction of
an act of law would commit the Riksdag to the programme over

12

s. 13 Kontrollera mot PDF

time. A new act of law should therefore be introduced that regulates,
among other things, the forms of the aid, i.e. central government
loans and two-way CfDs. The new act should also regulate the
conditions governing access to the aid and, to some extent, what
must be included in an application in more detail. The Inquiry also
proposes that an information provision be introduced that the
Government or the authority designated by the Government
pursuant to Chapter 8, Art. 7 of the Instrument of Government may
adopt additional provisions on what an application should include.
The proposal does not entail the Government being given
expanded powers compared to its powers under the Budget Act
since, unlike capital injections and acquisitions of shares, the forms
of aid proposed do not require the approval of the Riksdag in each
individual case. The Riksdag’s decisions on appropriations and
framework loans for the proposed forms of aid set the limits on
these amounts.
The Government should decide on aid
Pursuant to Chapter 17, Section 1 of the Swedish Environmental
Code, the Government is to consider the permissibility of, among
other things, installations for certain nuclear activities. This includes
new nuclear reactors (see Chapter 7). Provisions governing this
examination scheme were previously included in acts of law that
were repealed in connection with the introduction of the
Environmental Code. However, the scheme itself was transferred to
the Code unchanged. When the examination scheme was
introduced, it was justified by the fact that no other body than the
Government could effect a comprehensive examination that
balanced environmental, labour market policy and regional policy
views. In particular, it was considered important that rulings of this
kind should be made by one body that can be held accountable
politically.5
It can thus be concluded that the issue of the construction and
operation of new nuclear reactors entails clear policy trade-offs.
Since the possibility of receiving state aid is more or less a
5

See Govt Bill 1972:111, Appendix 2, p. 361 f, Report 1972Cu:35, Written communication
from the Riksdag 1972:348 and Govt Bill 1997/98:45 Part 1 pp. 435–437.

13

s. 14 Kontrollera mot PDF

prerequisite for the construction of new nuclear reactors, the
Inquiry assesses that the Government should be the body that
examines the basis for granting aid.
As previously mentioned (see Chapter 7), the Land and
Environment Court and the Swedish Radiation Safety Authority
prepare applications for licences under the Swedish Environmental
Code and the Nuclear Activities Act, and express their opinions on
the applications when submitted to the Government for
examination. The Inquiry has considered an equivalent scheme for
the examination of applications for aid in this instance. However, it
has not been possible to identify any suitable government agency
with the competence to make a comprehensive assessment of
received applications.
An alternative could be to set up a new government agency with
the necessary competence to provide a comprehensive opinion on
received applications to the Government. However, given that there
are uncertainties about the likely number of applications, the Inquiry
assesses that it is more appropriate, at least initially, for applications
to be submitted to the Government, which in turn can prepare the
applications received with the support of relevant government
agencies and, in addition, authorise them to conclude the necessary
agreements with the companies found eligible for aid. The
Government is also best placed to coordinate the application process
with the budget process.
Conditions for being allocated aid
The Inquiry’s proposal means that, if there are grounds for this, the
Government may decide to grant aid to companies for investments
in activities related to the construction and operation of one or more
new nuclear reactors with total installed capacity of at least
300 MWe. The Inquiry assesses that the Government’s processing
of applications and subsequent state aid investigation will be
resource-intensive, which motivates a minimum project size. This
does not rule out the inclusion of small modular reactors (SMR) in
a project as long as the total installed capacity of at least 300 MW.6
6

300 MW coincides with Svenska kraftnät’s threshold for connection to the 400 kV
transmission network.

14

s. 15 Kontrollera mot PDF

In addition, aid may be granted on condition that, at the time of
the decision concerning aid, the activity is covered by a licence under
the Nuclear Activities Act and is permitted under Chapter 17 of the
Swedish Environmental Code. As part of the licence application
procedure under the Nuclear Activities Act, a comprehensive
assessment of the applicant’s capacity to carry on the activity is
carried out (see Chapter 7). The fact that this condition must be
fulfilled thus means that the applicant has already, to some extent,
undergone an examination by the Government and has been found
to be suitable. In addition, in its permissibility assessment under the
Environmental Code, the Government will have settled on the
choice of site and assessed it as suitable from an environmental
perspective. This requirement also means that the Government can
ensure that an activity granted aid does not in itself breach any EU
provisions in the environment and energy area, since this is part of
the assessment of whether or not the proposed aid measure is
permitted under the TFEU (see Chapter 7).
Furthermore, aid may not be granted to companies that carry on
activities other than those to which the investment relates. This can
preferably be achieved by carrying on the activity in a separate
company. This condition is important for several reasons: firstly to
enable central government to more easily monitor the costs that
arise and to ensure that the funds are not used for purposes other
than those intended. Secondly, applying the risk-sharing mechanism
(see Section 9.5.3) in the proposed aid model is considerably
facilitated if the activity is carried on in a separate company. Thirdly,
it means that the company that is eligible to receive the aid can have
more than one owner to share the risk. Additional reasons are that
the investment in nuclear power is clearly separated from the owner
company’s other activities, which increases transparency and
facilitates ratings and analyses by credit rating agencies and other
external actors and financiers.
Since the aid is financed from public funds, it is important that it
is only given to companies with responsible owners and
representatives. Aid should therefore be granted to a company only
after a suitability assessment of a particular subset of the owners and
representatives of the company. The subset to be assessed should
include the owners who have a qualifying shareholding in the
company and persons who are members of the company’s board or

15

s. 16 Kontrollera mot PDF

management team. The assessment should cover these owners’
capacity to exercise responsible ownership and these representatives’
capacity to run the activity in a responsible manner. This means,
among other things, that the owner or owners must be assessed to
be honest and upright persons of integrity, and have the economic
capacity necessary to utilise the granted licence and pursue the
project to completion. To prevent foreign investments that could
affect Sweden’s national security or public order and public safety,
there are also applicable provisions in the Act on Screening of
Foreign Direct Investments (2023:560). In its owner assessment, the
Government must take these provisions into account.
As mentioned above, the Inquiry proposes that the Government
examines the question of whether aid can be granted to a company.
For the Government to be able to assess it, an application needs to
include a business plan which states the expected revenues and
expenses. Expected revenues and expenses means the weighted
average of the possible outcomes assumed for the calculation. The
business plan must also list significant risks, including how these
arise, are measured and managed. The Inquiry believes that the large
cost overruns that have affected recent nuclear power projects can
partly be explained by systematic underestimations of the costs of
new nuclear power. Requiring through regulation that expected
values are unbiased estimates clarifies what is expected in the
business plan, which also gives the Government a better basis for
assessing and comparing applications. It is the Government’s
responsibility to decide whether additional provisions are needed to
regulate the content of the application. The Government’s decision
should include an established capital cost that forms the basis for
decisions on framework loans in the Debt Office (see further
Section 9.5.1).
No right to appeal
The proposed act of law would mean that the Government decides
on aid for investments in new nuclear power. The Riksdag’s decision
on appropriations and framework loans for the forms of aid set
limits on the possibility of accessing all of the aid.

16

s. 17 Kontrollera mot PDF

According to Article 6(1) of the European Convention on
Human Rights, which applies as law in Sweden, there is a right to
judicial review of certain decisions. The Article is applicable where
there is a real and serious dispute over a right under national law and
where that right can be characterised as a civil right. The Inquiry
does not consider that a decision on aid for investments in new
nuclear power would constitute a civil right within the meaning of
the European Convention’s Article 6(1). Furthermore, the design of
the aid speaks against permitting a judicial proceeding. In light of
this, decisions under the proposed new act ought not to be
appealable.

9.5

Components of the financing model

9.5.1

State loans

Proposal: The Government is authorised by the Riksdag to
decide on loans in the Debt Office amounting to a maximum
of SEK 600 000 000 000 at the 2023 price level for investments in
new nuclear power. The subsidisation of interest and charges
should be financed from appropriations.
In connection with the Government’s decision to grant aid to
a company, the Debt Office should be tasked with issuing and
administering loans to companies found eligible for aid. The
loans to each company eligible for aid may amount to a maximum
of 75% of the capital cost established in the Government’s
decision to grant the aid, including a reserve for cost overruns up
to 100%. The loans should also cover the expected accrued
interest expenses during the construction phase.
The loans are to be issued in accordance with the following
terms and conditions.
- Up until two years post the start of commercial operation of
the first reactor in the project, the interest rate is to correspond
to central government’s financing cost for borrowing with the
equivalent maturity.
- Two years after the start of commercial operation of the first
reactor in the project, the interest rate is to be gradually increased
by an annual increment of 0.25 percentage points on top of

17

s. 18 Kontrollera mot PDF

central government’s financing cost. The increment is to have a
ceiling of 4 percentage points.
- Up until the start of commercial operation, interest expenses
are accumulated and added to the loan amount.
- The loan is to be repaid according to a fixed instalment
profile over the reactor’s projected operational life after coming
online.
- The borrowed amount may not be used for any other
purpose than that decided by the Government.
- The amount lent may not be used for profit transfers or
bonus schemes for senior executives of the company prior to the
first valuation of the company, which regulates the risk- and gainsharing mechanism. The same applies during periods when the
risk- or earnings-sharing mechanism is activated.

Reasons behind the proposal
Decisions on loans
As described in Section 9.4.1 it is proposed that the financing model
covers aid for new nuclear power with a total capacity of 4 000 to
6 000 MWe. Assuming that the total investments in new nuclear
power amount to 5 000 MWe, corresponding to the midpoint of the
proposed interval, the Inquiry estimates an expected borrowing
requirement of approximately SEK 300 billion at the 2023 price
level.7 However, the framework loan for an individual project must
include a reserve of 75% of the project’s costs up to a cost overrun
of 100%. It is considered unlikely that all projects would experience
such large cost overruns. Nevertheless, in order for the size of the
announced programme to be deemed credible, the Inquiry considers
that the total framework loan should contain a reserve that covers
central government’s maximum commitment under the financing
model, given that the programme is fully subscribed. In light of this,
in the annual budget bill the Government should be authorised to
decide on loans in the Debt Office amounting to a maximum
of SEK 600 billion at the 2023 price level. Depending on when the
investment is made, the framework loan needs to be adjusted
7

Based on a 75% proportion of debt capital and a capital cost corresponding to SEK 80 million
per MWe (see Chapter 5).

18

s. 19 Kontrollera mot PDF

upwards to the price level for the year. An alternative to authorising
the Government to decide on loans in the Debt Office within a
larger framework loan is that the Government is authorised in each
individual case to decide on loans to the companies found eligible
for the aid. However, the Inquiry considers that this arrangement
would be too time-consuming and therefore recommends that the
Government be authorised to decide on loans within the proposed
framework loan. This gives the Government the opportunity to
instruct the Debt Office to issue and administer loans to individual
companies directly in connection with the decision to grant aid
being made.
It is proposed that interest and charges are subsidised (see further
below). The Inquiry assumes that the lending will be managed within
the Swedish guarantee and lending model. This means that the
subsidy must be financed from appropriations. It is the
Government’s responsibility to earmark a suitable appropriation for
this purpose in the budget bill.
Capital structure
Shareholders in a company typically require a higher return on
equity than a lender does for loans to the same company. If the
proportion of debt capital increases, lenders normally require a
higher rate of return. The interest rate on the state loan corresponds
to central government’s financing cost. From an owner’s
perspective, a high proportion of debt capital in the form of state
loans is advantageous because, given an unchanged central
government interest rate, it lowers the total cost of capital for the
company eligible for the aid. The lower cost is because central
government is not compensated for the higher risk that a larger
proportion of debt capital entails. When selecting an appropriate
proportion of debt capital, central government must take into
account that a higher proportion increases government’s exposure
and that the owners’ incentives may be adversely affected. It can be
noted that the capital structure of companies comparable to the
major Nordic energy companies on average includes a proportion of
debt capital of 45%8. Furthermore, it can be noted that the capital
8

According to data from the annual reports of comparable energy companies.

19

s. 20 Kontrollera mot PDF

structure of European nuclear projects that have state loans as a
component differs from the average for European energy
companies. The Olkiluoto 3 nuclear power project in Finland had a
75% proportion of debt, while the Dukovany project in the Czech
Republic is initially expected to have a proportion of debt of 98%.
As described in previous chapters, investments in new nuclear power
are marked by greater uncertainty and higher risks when compared
to other types of generation, which increases the return required by
owners and lenders. This means that it is not possible to achieve
profitability in Swedish nuclear power projects without a financing
model that leads to significantly lower required returns. The predetermined capital structure of the company eligible for aid
(hereinafter referred to as the ‘project company’) should therefore
consist of a larger proportion of debt through state loans than of
equity from the owners of the project company. The Inquiry’s
assessment is that the capital structure ought to be 75% debt and
25% equity.
A distinction needs to be drawn between the capital structure in
the construction phase, where the entire debt consists of state loans,
and the operational phase, during which the project company is
expected to replace the state loans with market financing. There are
no guarantees that the project company can finance itself on the
open market with the capital structure that applied during the
construction phase. If the market requires a higher proportion of
equity, this will mean a lower return on equity in the operational
phase.
The Debt Office and the project company are the contracting
parties under private law for the state loans and thus the loans are
given directly to the project company. Therefore, no guarantee from
the project company’s owners is required, which reduces the risk and
cost of capital for the owners of the project company, as they risk
only their invested equity. This means that it is central government
that bears the risk in the loans that the borrower cannot meet its
obligations.

20

s. 21 Kontrollera mot PDF

Figure 9.2

Illustration of legal structure

Source: Own illustration.

The financing model makes it possible for the project company to
have one or more owners; and be structured as a subsidiary, joint
venture, separate company for special purposes or other suitable
legal type of company. Where the project company has multiple
owners, the company’s own capital investment, risk exposure and
required return can be reduced for each owner company. The
proposed model also does not rule out the possibility of central
government investing capital in exchange for shares in the project
company through a state-owned venture capital enterprise, and
functioning as an active owner for a shorter or longer period.
A separate project company where the investment in nuclear
power is clearly separated from other activities makes it easier for
rating agencies and other external actors and financiers to analyse
and assess the ordinary activities of the owner companies as their
engagements are limited to the equity they have invested. However,
how much influence the owners have in the project company; or
how the terms and conditions for dividends, other capital flows, and
agreements are stipulated affects this; also too if the project
company’s accounts must be consolidated in the financial
statements of the owner companies. The proposed terms and
conditions for the framework loan – that the project company may

21

s. 22 Kontrollera mot PDF

not use the loan amount for dividends or for purposes other than for
the project approved by the Government – strengthen the reasons
for considering the project company to be separate from the
ordinary activities of the owner companies.
Central government loan financing during the construction phase
After a project application has been approved, state loans can be paid
to the project company to finance the project’s capital costs. 75% of
the capital costs are financed by state loans, and the remaining 25%
are financed by equity through contributions from the project
company’s shareholders. It should be possible to deduct any capital
costs borne by the project company before the state loans were
granted from the established proportion of equity capital, and thus
also be financed with loans up to 75%. Figure 9.3 illustrates how the
project company finances the capital costs for the construction of
the nuclear power plant through regular contributions of debt and
equity capital.
Figure 9.3

The project company’s balance sheet during the construction
period
Normalised capital cost = 100 units

Note: Example with a five-year construction period where the capital costs arise in equal parts each
year during the construction period and are financed with 75% debt capital and 25% equity capital.

The project company is assessed as being best informed about the
time profile and the size of the project’s expected capital costs.

22

s. 23 Kontrollera mot PDF

Therefore, within the given terms and conditions for the state loans,
the maturities of the loans should be chosen by the project
company.9
The interest rate on the loans should correspond to the central
government's financing cost for borrowing at the chosen maturity.
Thus, the interest rate must not include an increment for expected
losses or administrative costs as expressed in the Budget Act
(2011:203) and in the Lending and Guarantees Ordinance
(2011:211). These terms and conditions – that the project company
borrows at the risk-free rate in Swedish kronor – apply throughout
the construction period. The favourable interest terms, which the
project company could not have obtained through market financing,
reduce the cost of the debt capital and thus the weighted average
cost of capital (WACC) for the project.
During the construction period, the project company generates
no revenue. In order to reduce the cash flow impact for the owner
companies, no interest is paid during the construction period.
Instead, the interest accumulates and is added to the loan amount.
This may cause the proportion of equity capital to temporarily drop
below the lower threshold of 25%. For practical reasons, it may
therefore be reasonable to permit minor deviations from the agreed
proportions of debt and equity capital for a short period of time. The
framework loan for the project needs to take into account the fact
that interest expenses will accumulate during the construction
phase.
The framework loan for a project includes a reserve for up to
100% cost overruns. Given that the costs in the application for the
programme are given at the unbiased expected value, the probability
that the ceiling for the framework loan will be reached ought to be
low. If the project’s framework loan nevertheless does not turn out
to be sufficient, the Riksdag may authorise the Government to
increase it, but potentially with different loan terms that are not
regulated within the model.
The proportion of equity capital in relation to debt capital must
not decrease as a result of cost overruns. Given that the shareholders
of the project company provide 25% equity capital, central
government will provide 75% debt capital. However, larger cost
9

However, it may be reasonable for the Debt Office to set an upper limit on the choice of
maturity to exclude excessively long maturities that are difficult to price.

23

s. 24 Kontrollera mot PDF

overruns affect the return on equity that the project company
receives in other parts of the risk-sharing model (see Section 9.5.3).
In addition to the ceiling for the framework loan, in practice
central government’s engagement is limited by the owners of the
project company needing to co-finance the cost overruns with
injections of equity. If the shareholders lack the will or the capacity
to inject additional equity, meaning that a 25% proportion of equity
capital is no longer reached, through the Debt Office as the sole
lender to the project company, central government can declare the
project company bankrupt. Other alternatives are that the Riksdag
authorises the Government to contribute equity capital to the
project company or that the equity capital is permitted to fall below
25%. However, the financing model does not regulate the terms and
conditions in cases where the owners do not contribute equity
according to the pre-agreed capital structure.
Central government loan financing during the operational phase
Once commercial operation of the nuclear power plant starts, 10
incentives to replace the state loans with market financing are
initiated through a progressively higher interest rate premium being
applied to central government’s financing cost, up to a ceiling. A
slow rate of increase means a lower interest rate on debt capital
compared to market financing and over a longer period, which
lowers the cost of capital for the project company. A faster rate of
increase means that the project company replaces the state loans
with loans from the private sector, which lowers the national debt.
The Inquiry proposes an annual increment of 0.25 percentage points
up to a ceiling of 4 percentage points, which gives a total phase-in
period of 16 years from the valuation date before the interest rate
ceiling is reached.
10

The start of commercial operation means the same here as in the proposed new Nuclear
Technology Act (SOU 2019:16, Chapter 5, Section 12). Starting commercial operation is the
final step in the Swedish Radiation Safety Authority’s step-by-step examination (see the
Swedish Radiation Safety Authority, Beredning av tillstånd och prövning av tillståndsvillkor
gällande kärntekniska anläggningar och andra komplexa anläggningar där strålning används
(Preparation of licences and examination of licence conditions for nuclear technology and
other complex installations using radiation) 6 May 2010). Somewhat simplified, the start of
commercial operation is when the nuclear reactor is commissioned for continuous commercial
operation.

24

s. 25 Kontrollera mot PDF

However, as illustrated in figure 9.4 the expectation is that the
state loans will be phased out earlier than the point in time when the
interest rate ceiling is reached. As the project progresses, uncertainty
and thus the return required by private lenders will decrease. When
the nuclear power plant is commissioned and starts generating cash
flows, the conditions for the project company to borrow on the
open market ought to be significantly better than during the
construction phase. Based on an estimated credit risk premium in
the interval 1–3 percentage points for the project company once its
nuclear power plant has gone online, the transition to market
financing is expected to occur within 4–12 years from
commissioning. Otherwise, central government will continue to
lend to the project company at a premium that generates a surplus
for central government.
Figure 9.4

Interest rates during the construction and operational phases
Percentage rate, not specified levels

Note: In the figure, the risk-free rate is constant but will vary over time for loans that are not at fixed
rates.Source: Own illustration.

The Inquiry assesses that a reasonable starting point is straight-line
amortisation of the state loans over the plant’s projected operational
life. The yearly repayment amounts are therefore set as the nominal
amount of the loan divided by the projected operational life of the
nuclear power plant. If some of the state loans are replaced by

25

s. 26 Kontrollera mot PDF

market financing, the repayment amounts on the remaining loans
are to be set as the amount of the loan divided by the remaining
projected operational life.
If the project company has chosen to fix the interest rate with
long maturities, situations may arise where the market rate is lower
than the interest rate on the state loans. In such cases, the project
company should be able to redeem parts or all of the loan amount
early. In order to incentivise the project company to adapt its choice
of maturities to its anticipated cash flow needs, the Inquiry assesses
that a reasonable starting point is that the project company should
bear any costs associated with early redemption of the loans. This
does not prevent central government and the project company from
agreeing on different repayment terms at a later date.11
Efficient use of funds and prohibition on profit transfers
The amount borrowed may not be used for any purpose other than
that decided by the Government, which should be monitored by the
Debt Office each time funds are drawn down from the loan facility.
The amount borrowed may not either be used for profit transfers or
bonus schemes for senior executives of the company before the
initial valuation of the company. There should be separate
monitoring to counteract covert profit transfers between the project
company and its owners via transactions not on market terms.

11

On the one hand, central government may have a preference for early repayment which
reduces central government debt; on the other hand, early repayment is likely to occur in a
scenario where market interest rates have fallen compared to the fixed interest rate on the
loan, which means a loss of revenue for central government.

26

s. 27 Kontrollera mot PDF

9.5.2

Price hedging arrangements

Proposal:
Design of the CfD
The Government is authorised by the Riksdag to enter into a
two-way financial contract for difference (CfD). The strike price
amounts to 80 öre/kWh at the 2023 price level and is to be based
on a reference capacity of 89%.
To determine the size of the compensation under the CfD,
the strike price is credited against a reference price. This may
result in an expense or income for central government depending
on whether the strike price is higher or lower than the reference
price.
The reference price is the yearly average electricity price in the
generator’s bidding zone on the day-ahead market. For the above
provisions to apply, the CfD must stipulate that the production
must be sold on the open power exchanges. The duration of the
CfD is to be 40 years from the planned start of commercial
operation. The CfD comes into force at the start of commercial
operation.
The general provisions in the CfD should not apply during
years when the nuclear power generator has not participated in
the power exchanges at all.
From six years post commercial operation being achieved, the
reference capacity is to be calculated on the basis of the five-year
average of the actual capacity factor for hours with positive
prices. For each subsequent year, the reference capacity is
calculated on the basis of the capacity factor during the previous
five years.
Financing of central government’s expenditure for the CfD
To finance central government’s expenditure for the CfD, a tax
proportional to the volume of electricity consumption should be
introduced to the extent it is possible. As far as possible, the tax
should encompass the entire Swedish electricity customer
collective.
Central government’s revenue from the nuclear power generator
under the CfD In the event that the average price level exceeds

27

s. 28 Kontrollera mot PDF

the strike price, the nuclear power generator is to compensate
central government in accordance with the principles evident in
the design of the CfD.
Calculation of tax levied
The tax should be set so that the net amount of the expenditure
and revenue generated by the CfD corresponds to the tax
revenues.
The nuclear power generator’s withdrawal options
In the event that the nuclear power generator enters into other
arrangements for hedging purposes, such as power purchase
agreements (PPA), during the term of the CfD, the volume
encumbered in those arrangements is to be deducted from the
reference capacity. However, during the term of the CfD the
share of generated electricity that is sold on the open power
exchanges must exceed 70%.

Reasons behind the proposal
Design of the CfD
A hedging arrangement is entered into to create predictability for
generators and provide consumers with some protection against
high electricity prices. One form of hedging arrangement is the
contract for difference or CfD. 12 A CfD means that the difference
between the market price and the strike price is paid by and to the
parties who have entered into the contract. The EU’s Electricity
Market Design Regulation (Regulation 2024/1747) highlights CfDs
as a potential alternative for incentivising investments in new
electricity generation.13 CfDs can be designed in a variety of ways
depending on which features are prioritised. Two factors are
particularly important to take into account in the design of CfDs
under the provisions of the Electricity Market Design Regulation.
One is that the CfD must be designed to preserve market incentives
as far as possible. The other is that they are to be two-way in the
sense that payments are transferred in both directions – between the
12
13

For additional background on CfDs, see Chapter 8 Financing and risk-sharing models.
See Chapter 7 Legal requirements concerning how CfDs relate to the state aid rules.

28

s. 29 Kontrollera mot PDF

consumer and the generator – depending on whether the market
price has been higher or lower than the strike price.
At the same time, the CfD must be designed to ensure that its
purpose – to enable the establishment of new energy production – is
achieved. The CfD does this by reducing the market risk and
contributing to an adequate, expected return on the invested capital.
The Inquiry assesses that a financial CfD is a suitable means of
reconciling these factors. The remuneration paid under the CfD is
based on a reference capacity, a strike price, and the average market
price. This increases predictability for electricity consumers and
generators while preserving market incentives as far as possible.
The design of the CfD is based on the following principles:
• The nuclear power generator sells electricity on the open market,
for which it receives the market revenue.
• Nuclear power has a capture rate close to 1. A capture rate of 1
means that the average revenue for a type of generation
corresponds to the average electricity price. A capture rate under
1 means that the type of generation has largely produced
electricity when prices have been low and a capture rate over 1
means the generation has largely occurred when prices have been
high.
• After a period of time, in this case a calendar year, the average
market price is calculated. If the average market price is below the
strike price, the nuclear power generator will be remunerated in
the amount of the difference multiplied by a reference capacity
and the hours in the calendar year. The reference capacity is set
based on the projected production from the nuclear power plant.
Where the average market price is above the strike price, the
nuclear power generator will remunerate central government in
the amount of the difference multiplied by the reference capacity
and the number of hours.
• The remuneration paid under the CfD is thus largely unrelated
to the generator’s actions. Consequently, the generator will act
in a way that maximises its earnings from sales on the open
market. The generator’s response to market signals is thus not
distorted more than necessary by the CfD.

29

s. 30 Kontrollera mot PDF

Figure 9.5

Example of a financial CfD

Note: Average electricity price 67 öre/kWh in the generator’s bidding zone and contracted difference
level of 80 öre/kWh. The CfD means that the area a multiplied by a predetermined capacity factor is to
be transferred. Source: Own illustration.

In the example shown in figure 9.5 the average price level in the
nuclear power generator’s bidding zone was 67 öre/kWh over the
past year. 67 öre/kWh corresponds to the electricity price in bidding
zone SE3 in 2045 in Svenska kraftnät’s Plannable Electrification
(PE) scenario.14, 15 The strike price in the CfD in the example is
80 öre/kWh. In this case, the value of the remuneration in SEK to
be paid under the CfD is given by the following equation:
𝑅𝑒𝑚𝑢𝑛𝑖𝑟𝑎𝑡𝑖𝑜𝑛 = (0.80 − 0.67) ∗ 8 766 ∗ 1 250 000 ∗ 89 %
where 8 766 is the number of hours in a typical year, the nuclear
power plant has an installed capacity of 1 250 MWe (1 250 000 kWe)
and the reference capacity is 89%. In the example, the remuneration
received by the nuclear power generator would be SEK 1.27 billion.
Given that the CfD is two-way, the nuclear power generator would
remunerate central government in the amount of SEK 1.27 billion if
the average electricity price had instead been 93 öre/kWh.

14
15

Svenska kraftnät (2024a). Långsiktig marknadsanalys (Long-term market analysis).
The exchange rate applied is SEK 11 to EUR 1.

30

s. 31 Kontrollera mot PDF

Along with the revenue or expense tied to the CfD, the total
revenue for the nuclear power generator is determined by the market
revenue it receives. The size of the yearly market revenue can be
expressed as a function of the average electricity price, capture rate
(cr), capacity factor (cf), installed generator capacity (igc) and the
number of hours in the year.
𝐴𝑛𝑛𝑢𝑎𝑙 𝑚𝑎𝑟𝑘𝑒𝑡 𝑟𝑒𝑣𝑒𝑛𝑢𝑒
= 𝑒𝑙𝑒𝑐𝑡𝑟𝑖𝑐𝑖𝑡𝑦 𝑝𝑟𝑖𝑐𝑒 ∗ 𝑐𝑟 ∗ 𝑐𝑓 ∗ 𝑖𝑔𝑐 ∗ 8 766
The average electricity price in the example is 67 öre/kWh. Given a
capture rate of 1, a capacity factor of 89% and 1 250 MWe of
installed generator capacity, the market revenue amounts
to SEK 6.5 billion. Under these conditions, with a financial CfD the
total revenue is equivalent to that obtained with a productionbased16 CfD where production is remunerated at a fixed strike price
and the total revenue for a given production volume is the same
regardless of what the market prices were at the time of the
production.
If the nuclear power generator responds to market signals by
setting yearly maintenance periods when prices are low or investing
in a flexible power plant, thereby achieving a capture rate over 1, the
total revenue with a financial CfD will be higher than with a
production-based CfD. 17 However, it is expected that the most
rational choice for the nuclear power generator will still be to strive
for as high a capacity factor as possible, provided that the market
demands its production. The incentives emanating from the price
signals contribute to a more efficient electricity market and a more
stable electricity system.
The Inquiry assesses that hedging arrangements are necessary to
manage the market risk to a degree that will permit investments in
new nuclear power to be made. If not taken into account, the market
risk would weigh down the investment calculation for nuclear power
due to the long time horizons over which the project operates and
the large investments required for new nuclear power. A financial
CfD is proposed because the Inquiry assesses that the price signals
16

A production-based CfD means that the generator receives an income equal to the strike
price for each unit of energy produced.
17
Given that the actual capacity achieved has not exceeded the reference capacity to the
equivalent degree.

31

s. 32 Kontrollera mot PDF

from the electricity market should be preserved as far as possible in
order to promote efficiency and stability in the electricity system.
This design is also assessed as contributing to compliance with
the provisions in the EU’s Electricity Market Design Regulation.
Based on the expected costs and taking into account the risk sharing
and financing involved in the Inquiry’s proposal, a strike price
of 80 öre/kWh is seen as generating enough remuneration for a
nuclear power project to provide the return required for the
investment to be made.
The fact that the strike price is slightly higher than indicated in
scenario analyses18 of future electricity prices can be justified socioeconomically by the external benefits that are not fully reflected in
today’s price signals. Furthermore, the additional plannable power
increases the likelihood of achieving the Government’s energy
policy planning target of 300 TWh because expanding renewable
electricity to the extent that would be required to reach the target
has its challenges. Even if such an expansion of wind power were to
prove possible, there is a risk that balance in the system cannot be
achieved with this energy mix unless electricity prices periodically
move very high, or unless costly ancillary services are brought online
to ensure stability. It is proposed that the average market price is
defined per calendar year because it is assumed that the nuclear
power generator’s capacity factor corresponds to the reference
capacity on a yearly basis. In addition, central government
expenditure is budgeted on a yearly basis.
The average market price multiplied by the reference capacity
constitutes an estimate of the revenue that the nuclear power
generator is expected to obtain on the market, given that production
occurs randomly for the number of hours in the year that
corresponds to the reference capacity, i.e. the capture rate is 1.
In the event that the nuclear power generator optimises its
production in relation to market prices, for example, by planning
yearly maintenance production stoppages when the electricity price
is low, the total average revenue may exceed the strike price. At the
same time, the total revenue could fall below the strike price in the
event that the nuclear power generator fails to optimise its
production. This is a necessary consequence of preserving incentives
in the electricity market.
18

Svenska kraftnät (2024). Långsiktig marknadsanalys (Long-term market analysis).

32

s. 33 Kontrollera mot PDF

Since nuclear power plants have a capture rate close to 1, the
unweighted average price is a suitable estimate of the expected
revenue.
It is proposed that the average market price is calculated on the
basis of the prices on the day-ahead market for the bidding zone in
which the generator is located. The reason for using the prices on
the day-ahead market is that the day-ahead market is the main
market for electricity trading in the Nordic countries. The prices on
the day-ahead market are therefore the best approximation of the
generator’s market revenue. If the electricity market changes such
that the day-ahead market no longer meets this criterion, the market
that replaced the day-ahead market and is the largest in terms of
volume traded should be used to determine the reference price. The
reason for using the bidding zone in which the generator is located
to calculate the reference price is that the revenue the generator
receives from the market is specific to that bidding zone.
In connection with its examination of applications for aid, the
Government must assess whether there are grounds for granting aid
to the individual project. The examination can take into account
whether the level in the CfD is justified based on the individual
project’s circumstances, given its contribution to the electricity
system among other things.
For the Government to be able to enter into a CfD, an
authorisation from the Riksdag to place orders is required for the
period to which the CfD relates and for the forecast expenditure that
the CfD is expected to entail. A contract duration of 40 years is in
line with the Czech Republic’s model which has received state aid
approval from the European Commission. When deciding on the
contract duration, a balance needs to be struck between the duration
and the level of the strike price, as a shorter duration entails higher
uncertainty for investors and thus higher risk premiums. The reason
for proposing that the contracted duration should apply from the
planned start of commercial operation19 is partly to create incentives
for market players to submit unbiased estimates for the construction
time in their applications to participate in the financing and risk-

19

This means that the actual contract duration can be longer than 40 years if commercial
operation is achieved earlier than planned, and shorter if the start of commercial operation is
achieved later than planned.

33

s. 34 Kontrollera mot PDF

sharing model, and partly to provide additional incentives to carry
out the project efficiently and on schedule.
The Inquiry assesses that 89% is a reasonable starting point for
the capacity factor for new nuclear power. However, it is difficult to
estimate in advance what capacity factor the nuclear power plant will
actually achieve.
To reflect the achieved capacity factor in the reference capacity
while at the same time not influencing production decisions during
the current year based on the CfD more than is necessary, the
Inquiry proposes that the reference capacity should be set based on
the average of the previous five years’ capacity factors for the hours
that electricity prices have been positive. Hours with negative and
zero prices should be excluded from the calculation of the reference
capacity to ensure that there are no incentives to produce during
periods with negative prices. If hours with negative prices were to be
included, the generator would have an incentive to produce, even
when demand does not exist, in order to keep up its future reference
capacity.
The capacity factor achieved before the nuclear power plant has
started commercial operation should not be taken into account in
the reference capacity calculation. Therefore, from the time the
nuclear power plant starts commercial operation and for the
following five years, the reference capacity should instead be 89%.
Financing of central government’s payments under the CfD
The benefits that arise as a result of new nuclear power being added
to the production mix will be shared by the entire electricity
customer collective. Benefits such as increased system stability, the
ability to utilise existing network infrastructure more efficiently and
price stability are not fully priced into today’s market. The Inquiry
assesses that the costs should be shared in proportion to the benefits
that arise. Therefore, it is proposed that the electricity market’s
consumers should bear the cost in relation to their consumption.
Based on the practical factors associated with changes in tax rates, it
may be justified to deviate from being in balance on a yearly basis.
However, the Inquiry considers that it is still worth striving for the
revenues to correspond to the costs over time. This is because

34

s. 35 Kontrollera mot PDF

periods of high average prices on the market mean that central
government’s cost decreases or that central government receives
revenue from the generator. In periods where central government’s
cost under the provisions in the CfD is high, it is instead a
consequence of the average prices on the market having been low.
Thus, the total cost of electricity for electricity customers is evened
out between periods. The design of the CfD thus provides electricity
customers with some protection against high prices given that the
tax is reduced when central government receives revenue from the
nuclear power generators.
The Inquiry has considered financing the CfD by means of
designs that enable a clearer link and better alignment between
revenue and expenses. The two designs considered are levying
charges and certificate systems. Levying charges has been rejected
because of the Swedish requirement that levies need to be linked to
a clear counter-performance of which the levy directly covers the
costs, this is not deemed to be sufficiently clear. Certificate systems
have been rejected because there are deemed to be too few actors for
the market to function well. However, financing that allows the
revenue to correspond to the expenses is still seen as desirable.
Therefore, if solutions that involve levying charges or a certificate
system are identified, financing by these means should be
considered.
The required revenue per kWh as a result of entering into the
CfD may be expressed in the following equation:
ö𝑟𝑒
𝑅𝑒𝑚𝑢𝑛𝑒𝑟𝑎𝑡𝑖𝑜𝑛 ∗ 100
=
𝑘𝑊ℎ
𝑘𝑊ℎ 𝑐𝑜𝑛𝑠𝑢𝑚𝑝𝑡𝑖𝑜𝑛
where the remuneration is given by the equation above in the section
and is converted from kronor to öre and consumption refers to total
Swedish electricity consumption in kWh. Given the remuneration in
the example above (about SEK 1.27 billion) and the cost being
distributed over 300 TWh, the mark-up required to finance the
payment amounts to approximately 0.42 öre/kWh to remunerate a
nuclear power plant with 1 250 MWe installed generator capacity.
The mark-up is scalable based on the installed generator capacity,
the difference between the strike price and the market price, and the
total electricity consumption over which the payment is to be

35

s. 36 Kontrollera mot PDF

distributed. If the installed generator capacity amounts to
5 000 MWe, the mark-up will be approximately 1.68 öre if the
bidding zone price is 67 öre/kWh. If the bidding zone price is
instead 49 öre/kWh20, which is the lowest average price for SE3 and
SE4 in 2045 in Svenska kraftnät’s various scenarios21, and the strike
price remains at 80 öre/kWh, the mark-up per kWh will be
approximately 1 öre/kWh. To remunerate 5 000 MWe where the
bidding zone price is 49 öre/kWh, the necessary mark-up will be
4 öre/kWh. The mark-up per kWh also increases pro rata if the
remuneration is to be distributed over fewer TWh of consumption.
For example, if the cost is distributed over 150 TWh instead of
300 TWh, the necessary mark-ups stated above will double. The
amounts stated above correspond to the required tax revenue and
must therefore correspond to the tax including VAT in the event
that VAT is levied.
The nuclear power generator’s withdrawal options
It may be justifiable for the nuclear power generator to be given the
opportunity to enter into hedging arrangements, such as PPAs, for
parts of the production alongside the CfD. A demand for hedging
arrangements can be expected from, for example, new industrial
projects, and the Inquiry assesses that it is reasonable that nuclear
power companies are given the opportunity to satisfy this demand
to some extent. In addition, a gradual transition from CfDs to other
forms of hedging arrangement may reduce long-term price
uncertainty when the CfDs are about to expire. However, these
motives need to be balanced against the fact that the electricity
customer collective and central government have borne the risk
during the project and that the CfD is intended to give electricity
customers protection against periods with high electricity prices.
The Inquiry does not consider that there are grounds for allowing
the generator to enter into other hedging arrangements while their
production is being compensated at an unchanged level in
accordance with the provisions in the CfD. Therefore, it is proposed
that production that is hedged through arrangements outside the
20
21

At the 2024 price level with exchange rate of SEK 11 to EUR 1.
Svenska kraftnät (2024). Långsiktig marknadsanalys (Long-term market analysis).

36

s. 37 Kontrollera mot PDF

CfD should be deducted from the reference capacity. The reasons
why at least 70% of the production should be sold on the open
power exchanges are: that the electricity customer collective will be
able to share in the production due to the risk they bore during the
earlier phase of the project; and that in its approval of the Czech
nuclear power model the European Commission announced that
similar conditions must be implemented.
It is also possible to make changes to the provisions in the CfD
provided that the contracting parties agree, and that the changes are
compatible with the applicable legislation, including EU state aid
rules.
9.5.3

Risk- and gain-sharing mechanism

Proposal: The financing model should include a risk- and gainsharing mechanism that is regulated by the terms and conditions
in the loan agreement and the CfD.
Valuation
- Two Government-procured valuers estimate the market
value of the equity in the project company two years after the
start of commercial operation (the valuation date).
- The market value is set as the average of the two valuations.
Thresholds
- A lower threshold is calculated as invested equity in the
project company adjusted upwards by a real rate of return of 2%
and consumer price inflation (CPI).
- For cost overruns exceeding 50%, the lower threshold is
adjusted down by a real return of -2% and the CPI on the surplus
proportion of equity capital.
- An upper threshold is calculated as invested equity in the
project company adjusted upwards by a real rate of return of 15%
and CPI.
Restoration of equity mechanism (risk- and gain-sharing)
- If the market value on the valuation date falls below the
lower threshold, in the following year the interest rate on the

37

s. 38 Kontrollera mot PDF

state loans is reduced to the government’s financing cost, and the
strike price in the CfD is increased by 10%.
If it is not expected that the market value will be restored to
the lower threshold within five years, an enhanced risk-sharing
mechanism is activated, which lowers the nominal interest rate to
0% and raises the strike price by 20% for the next year.
- If the market value exceeds the upper threshold, the interest
rate will be increased to central government’s financing cost plus
an increment of 2 percentage points and the strike price will be
lowered by 20% for coming years.
- The need for the restoration of equity mechanism is tested
through annual valuations and remains activated until the market
value lies between the lower and upper thresholds. The annual
valuations determine whether the unenhanced or enhanced risksharing mechanism is to be activated.
- If the initial valuation shows that the market value lies
between the thresholds, neither the risk-sharing nor the gainsharing mechanism will be activated.

Reasons behind the proposal
If large cost overruns and delays have occurred during the
construction phase, one cannot rule out that the project company
will face long-term profitability problems at commissioning. Given
that only a few nuclear power projects have been implemented in
Europe in recent times, and that time and cost overruns for some of
these projects have been high, the returns required by private
investors is high. Experience from other countries shows that it may
be possible to bring about investments in new nuclear power solely
with a price hedging arrangement, but at a high price for electricity
consumers or taxpayers over long periods.22
A model that shares the risk in the case of poor outcomes during
the construction phase on the one hand leads to the project owner
lowering their required return, and on the other hand, to the
efficiency of the project potentially being negatively affected. The
22

For example, in Hinkley Point C, where the project owner EDF bears the risk of cost
overruns and delays, the strike price in the CfD measured in today’s prices amounts to over
150 öre/kWh for 35 years.

38

s. 39 Kontrollera mot PDF

Inquiry considers that a risk-sharing model that significantly
reduces the risk of the worst outcomes, but where the project owner
bears the risk of other negative outcomes, provides the best balance
between required return, efficiency and central government’s risktaking.
Given that central government and the electricity consumers bear
the risk of the worst outcomes, they should also be able to benefit
from the best outcomes. Beyond balancing the interests of the
various parties, there are additional reasons for an earnings-sharing
mechanism.
In its investigation of other countries’ financing models, the
European Commission has attached great importance to the
existence of mechanisms to prevent overcompensation. The
financing models approved by the Commission for Hinkley Point C
in the United Kingdom and Dukovany II in the Czech Republic
contain mechanisms to distribute any surplus23 between the
electricity generator, electricity consumers and central government.
In light of these decisions, the Inquiry assesses that the financing
model needs to include an gain-sharing mechanism in order to be
able to pass a state aid investigation.
Furthermore, uncertainty in the choice of parameters for the
hedging arrangement could justify an gain-sharing mechanism. The
terms and conditions for the strike price and duration are
determined at an early stage based on estimates of revenues,
expenses and required returns where the nuclear power industry
most likely will have an information advantage in the negotiations.
There is a risk that the terms and conditions are set too generously,
which would have an impact on the electricity consumer’s costs for
many decades. A mechanism that distributes surpluses that are
substantially above the expected return at the time of the investment
can mitigate such consequences.
The following sections describe and explain in more detail the
various components of the risk-sharing mechanism.

23

Surplus refers to return on equity that exceeds a predetermined level.

39

s. 40 Kontrollera mot PDF

Valuation
The risk- and gain-sharing mechanism is activated in scenarios where
the project company has had a significantly lower or higher return
on equity during the construction phase than was expected when the
loan agreement and the CfD were concluded. 24
Many of the risk-sharing models in the investigated countries
focus on cost overruns during the construction phase and allocate
responsibility for these by means of contractual terms or regulatory
supervision.25 However, time and cost overruns during the
construction phase do not necessarily result in long-term
profitability problems. Similarly, there are no guarantees that a
project that has kept to its schedule and budget will be profitable in
the long term. Factors affecting profitability – operating expenses,
the interest rate situation, taxes or the reactor’s availability – may
have changed permanently at the time the nuclear power plant comes
online. The Inquiry therefore considers that cash flows and return
on equity are more comprehensive and relevant metrics than merely
looking at cost overruns.
Therefore, two years after the nuclear power plant starts
commercial operation, a valuation of the project company is done.
The purpose of the valuation is to estimate the market value of the
project company’s equity. Market value is here defined to mean the
estimated amount for which an asset or liability should exchange on
the valuation date between a willing buyer and a willing seller in an
arm’s length transaction, after proper marketing and where the
parties had each acted knowledgeably, prudently and without
compulsion..26 In assessing the market value, the contractual terms
and conditions under the loan agreement and the CfD should be
taken into account.27
It is inevitable that a company valuation will be uncertain.
Assumptions need to be made about future revenues, expenses,
24

This refers to the return that would be obtained if the owners were to divest their shares in
the project company at the estimated market value at the time of valuation. Alternatively, the
shares are retained and the corresponding expected return is instead obtained over time by
sharing in future earnings (and dividends) with the same net present value as the market value.
25
The Czech model has contractual terms for “legitimate grounds”, while the UK’s Regulated
Asset Base (RAB) model is based on ongoing assessments by a regulatory authority. See
Chapter 8 for a discussion of these and other countries’ financing models.
26
International Valuation Standards Council (2022). International Valuation Standards (IVS).
27
However, the valuation is done on the assumption that the risk- and earnings-sharing
mechanism has not been activated.

40

s. 41 Kontrollera mot PDF

electricity prices, interest rates, taxes, required returns, etc.
However, the uncertainty in the project company’s cash flows will
be significantly lower at commissioning compared to the
uncertainty at the time of the investment. The construction costs are
known at commissioning. In addition, the CfD safeguards the
project company’s revenues for 40 years. The remaining
uncertainties in the valuation consist of assumptions about the
future availability of the reactor, operating expenses, loan-to-value
ratio and market-based required return on borrowed funds and
equity in the long term. In order to reduce the uncertainties
surrounding the reactor’s functional capacity, it is proposed that the
valuation be done two years after the start of commercial operation.
At this point, the first fuel change will have been done, which allows
a more precise assessment of how well the reactor is expected to
function in the future.
In order to reduce the uncertainty and the risk that any of the
parties could influence the outcome of the valuation, the Inquiry
proposes that two valuers are hired to value the project company.
The valuers are procured by the Government (or the authority
designated by the Government) but must carry out their valuations
independently of the project company, central government, and
each other. It is proposed that the valuation that forms the basis for
the risk and earnings sharing is set as the average of the two
valuations. An alternative that could be considered, in order to
further reduce uncertainty in the valuation, is to agree in contract to
procure a third valuer to supplement the average if the gap between
the two valuations is too great.
The Inquiry does not consider it appropriate to establish
conditions for the valuation in advance that are too strict, as this may
run counter to the aim of obtaining independent appraisals of the
market value of the project company. Conversely, a completely
unregulated approach to the valuation could create uncertainty for
the project owner about the method and assumptions that will be
used in the valuation, which reduces willingness to invest. It is
difficult at this stage to identify exactly which aspects might be
appropriate to regulate in advance. Ultimately, the design of loan
agreements and CfDs will be a matter for negotiation between
central government and potential investors. However, the Inquiry

41

s. 42 Kontrollera mot PDF

has identified some areas that it may be reasonable to regulate in
advance, and is of the view that the valuation:
• should take into account the terms and conditions of the
financing and risk-sharing model (expected revenue from the
CfD and interest terms for the central government loans)
because they have an effect on cash flow and thus affect the value
of the equity in the project company;
• should be carried out by valuers who have (or are able to procure)
expert knowledge about the nuclear power industry to ensure an
independent valuation not based on appraisals from the project
company. The valuation should be done with high quality and
transparency by a supplier with good professional experience.
This can be regulated in the contractual terms by requiring a
minimum annual turnover of valuation assignments.
• should be made on the basis of assumptions that are deemed to
be reasonably long-term in order to mitigate the effects of
temporary circumstances that may prevail at the time of the
valuation;
• should view the project company as an independent company
even if it is part of a group or has other implicit or explicit backing
from the owners. If not, the valuation risks reflecting the owner’s
rather than the project company’s assets.28
• it should primarily be based on a cash flow valuation. This does
not rule out the use of other supplementary valuation methods,
such as relative valuation. However, the Inquiry assesses that it is
challenging to identify companies and transactions that are
sufficiently comparable with the project company for it to be
appropriate to use relative valuation as the primary approach, and
• it is not appropriate to set parameters in advance, such as absolute
levels for interest rates, required return or price forecasts.
However, it may be reasonable to agree in advance on methods

28

For example, an owner could issue guarantees for the project company’s loans in order to
get a lower interest rate when the central government loans are replaced by market financing.

42

s. 43 Kontrollera mot PDF

and the data to be used as the basis for how certain parameters
are to be calculated.29
In other respects, the Inquiry assesses that it is most appropriate for
the contractual terms and conditions for the valuation in more detail
be submitted to the Government or the authority designated by the
Government.
The Inquiry is of the view that the proposed valuation model has
been adapted to meet the demands of the state aid investigation.
However, some uncertainty remains about the Commission’s
position and it cannot be ruled out that the proposed risk-sharing
model may need to be modified in some respect.
Lower threshold (floor)
In order to determine whether the risk-sharing mechanism should
be activated, the estimated market value of the equity is compared
with a lower threshold.
For cost overruns30 up to 50%, the threshold is calculated as the
amount that the invested equity in the project company would have
had on the valuation date if it had had a real return of 2% per year in
addition to consumer price inflation (CPI). For cost overruns of
more than 50%, the threshold value of the surplus invested equity is
calculated instead using a negative real return of -2%. In the case of
large cost overruns, the threshold will therefore be adjusted upwards
by a real return on invested equity of between -2% and 2%.31
The choice of raising factor and the threshold value for cost
overruns is a balance between protecting the project company’s
owners from adverse outcomes with long periods of very low or
negative returns, and providing incentives to run the project as
efficiently as possible. As a starting point, therefore, the return with
which the lower threshold is adjusted upwards should correspond to

29

To take an example, it may be reasonable to determine in advance the reference rate to be
used as the basis for the assumed risk-free rate in the weighted average cost of capital (WACC)
calculation and how it should be calculated, but not what it should be in absolute terms.
30
Cost overruns are calculated in relation to the expected costs established in the
Government’s decision to grant aid.
31
Given the ceiling of 100% cost overruns, in practice the increase will result in a positive real
return.

43

s. 44 Kontrollera mot PDF

a level that is substantially below the shareholders’ required return
on equity.
The fact that the adjustment upwards of the threshold penalises
large cost overruns gives the project company an incentive to submit
its best appraisal of expected costs at the time of application. A
further reason to punish higher cost overruns is that it is more likely
to screen out projects with large negative tail risks before the
application to participate in the financing and risk-sharing
programme is submitted. It is therefore seen as leading to a fairer
assessment of and comparison between applications to the
programme.32

32

Without such incentives, the project company could have an interest in understating the
expected costs in order to access the financing and risk-sharing programme.

44

s. 45 Kontrollera mot PDF

Example – Lower threshold calculation
Figure 9.6 illustrates the calculation of the lower threshold given
regular equity injections during the construction phase. This and
subsequent calculation examples are fictitious and have no
connection to the assessed costs or proposed parameters. A
summary of parameter choice and an overall assessment is done in
Section 9.6.
Figure 9.6

Calculation of lower threshold (floor)
Normalised capital cost = 100 units

Note: In this illustrative example, the valuation is done in conjunction with commissioning. However,
the Inquiry’s proposal is that the valuation is done two years after commercial operation starts.

In the example calculation, the project company invests 20 units
per year for a total capital cost of 100 units. This is financed by
75 units of debt capital and 25 units of equity capital. The
investments in equity are adjusted upwards during the
construction period and in the example amount to 10 units at the
start of commercial operation. The threshold is thus calculated as
35 units (25+10).

Upper threshold (ceiling)
Calculating the upper threshold works in principle in the same way
as calculating the lower one. It is calculated as the amount of the

45

s. 46 Kontrollera mot PDF

invested equity in the project company on the valuation date if it had
had a real rate of return of 15% per year on top of consumer price
inflation (CPI).
As mentioned above, the Inquiry considers that a gain-sharing
mechanism is necessary for the financing and risk-sharing model to
be eligible for approval in a state aid investigation by the
Commission. The Inquiry also sees advantages with such a
mechanism, as it can mitigate the effects of the contractual terms for
the CfD being set too generously.
At the same time, the earnings-sharing mechanism needs to take
into account the differences between the proposed Swedish model
and other countries’ financing models. The Czech Republic’s gainsharing mechanism lasts throughout the lifetime of the project. This
means that central government needs to monitor and revise the
terms and conditions of the contract throughout the lifetime of the
project of over 60 years. The same applies to the UK’s Regulated
Asset Base (RAB) model where a regulatory authority needs to
supervise the project from start to finish.
The financing model proposed here is based on well-targeted
incentives rather than supervision. Because the lower threshold is
adjusted upwards where the return is low, the worst outcomes are
eliminated, while by running the project efficiently the project
company has the opportunity to generate a higher than expected
return. An gain-sharing mechanism that removes too much of the
share in favourable outcomes reduces incentives for efficiency. The
ceiling determining when an earnings-sharing mechanism is
activated should therefore be adjusted upwards where the return
exceeds the expected return by a good margin.

46

s. 47 Kontrollera mot PDF

Example – Upper threshold calculation
Figure 9.7 illustrates the calculation of the upper threshold given
regular equity injections during the construction phase.
Figure 9.7

Calculation of upper threshold (ceiling)
Normalised capital cost = 100 units

Note: In this illustrative example, the valuation is done in connection with commissioning. However,
the Inquiry’s proposal is that the valuation is done two years after commercial operation starts.

As in the previous calculation example, the project company
invests 20 units per year, financed by 75% debt capital and
25% equity capital. Prior to commissioning, the accumulated
capital cost amounts to 100 units. The injections of equity are
adjusted upwards during the construction period and in the
example amount to 20 units in total at commissioning. The upper
threshold is thus calculated as 45 units (25+20).

Comparison between market value and threshold value
In order to determine whether the risk-sharing or the gain-sharing
mechanism should be activated, the estimated market value of the
equity is compared with the lower and upper thresholds at the time
of valuation. If the market value of the equity falls below the lower
threshold, a risk-sharing mechanism is activated which has its effect
through more favourable terms and conditions for the CfD and the

47

s. 48 Kontrollera mot PDF

central government loans. If instead the market value of the equity
exceeds the upper threshold, an ain-sharing mechanism is activated
which tightens up the terms and conditions for the CfD and the
central government loans.
Example - calculation of comparison between market value
and threshold value
The principles for a market value below the lower threshold are
illustrated in figure 9.8.
Figure 9.8

Market value below lower threshold (floor)
Normalised capital cost = 100 units

75

75

Note: In this illustrative example, the valuation is done in connection with commissioning. However,
the Inquiry’s proposal is that the valuation is done two years after commercial operation starts.

In the calculation example, the enterprise value of the project
company at the time of the valuation is estimated at 95 units
which is 5 units lower than the original value of 100 units. The
project company’s net financial debt (the state loans reduced by
any cash in hand) of 75 units is subtracted from this value,
resulting in a market value of the equity of 20 units. Since the
market value of the equity is lower than the lower threshold
(20<35), the risk-sharing mechanism is activated.

48

s. 49 Kontrollera mot PDF

The principles for the opposite scenario, where the market
value instead exceeds the upper threshold, are illustrated in
figure 9.9.
Figure 9.9

Market value exceeds upper threshold (ceiling)
Normalised capital cost = 100 units

75

75

Note: In this illustrative example, the valuation is done in connection with commissioning. However,
the Inquiry’s proposal is that the valuation is done two years after the start of commercial
operation.

In the calculation example, the value of the project company at
the time of valuation is estimated at 140 units, which is 40 units
higher than the original value of 100 units. The project company’s
net financial debt (the state loans reduced by any cash in hand) of
75 units is subtracted from this, resulting in a market value of the
equity of 65 units. Since the market value of the equity is higher
than the upper threshold (65>45), the gain-sharing mechanism is
activated.

If the project develops more in accordance with expectations and the
market value lies between the upper and lower thresholds, neither
the risk-sharing nor the gain-sharing mechanism is activated. The
risk- and gain-sharing mechanism can thus only be activated at the

49

s. 50 Kontrollera mot PDF

time of initial valuation, and any profitability problems that come to
light later must be dealt with by the project company on its own.
Risk-sharing mechanism
The risk sharing operates through two mechanisms: the interest rate
on the state loans is lowered and the strike price in the CfD is
temporarily raised. The higher income from the CfD and lower
interest costs add to the project company’s cash in hand, which
lowers the net financial debt. All else being equal, this increases the
value of the equity in the project company by the equivalent amount.
The choice of parameter values for reducing the interest rate and
increasing the strike price need to be seen in relation to each other
as they determine how the risk is distributed between central
government and the electricity consumers. A large reduction in the
interest rate relative to the increase in the strike price means that
central government bears a larger share of the costs of the risk
sharing, and vice versa. The Inquiry estimates that an interest rate
amounting to central government’s financing cost and a 10% higher
strike price would give a roughly expected balance between central
government’s and the electricity consumer’s obligations in the risksharing mechanism.
The risk sharing is activated until the market value of the project
company’s equity exceeds the threshold. The threshold is adjusted
upwards annually, just like in the construction phase, by 2% real
return and consumer price inflation (CPI).33
Once the risk-sharing mechanism is activated, a new valuation of
the project company is done each year. If the next valuation shows
that the value of the equity in the project company exceeds the
threshold, the risk sharing is terminated. It can only be activated
once – profitability problems that arise thereafter must be managed
by the project company’s owners themselves. The risk sharing thus
addresses the profitability problems realised during the construction
phase (such as cost overruns) and those anticipated to arise in the

33

Or -2% real return for the proportion of equity capital that finances cost overruns above
50%.

50

s. 51 Kontrollera mot PDF

future at the time of valuation (such as higher operating expenses).34
While the risk-sharing mechanism remains activated, the interest
rate on the state loans continues to be adjusted upwards by the
increments described in previous sections. This means that, after the
risk sharing is terminated, the project company confronts the
interest rate that would otherwise have applied without the risk
sharing.35
If the mechanism described above is not expected to result in the
market value of the project company’s equity exceeding the
threshold within a reasonable timeframe, an enhanced risk-sharing
mechanism is activated. The enhanced mechanism will enable the
project company to achieve a market rate of return faster. But this
also means a higher cost for central government and electricity
consumers. The Inquiry assesses that a reasonable timeframe to
restore the value is five years, i.e. if the unenhanced risk sharing is
not expected to result in the valuation exceeding the threshold
within five years, the enhanced risk sharing is activated. The
enhanced risk-sharing mechanism works in the same way as the
unenhanced, but with more generous levels, which means that the
value of the project company’s equity is restored at a faster rate. The
Inquiry considers that a powerful, enhanced risk-sharing mechanism
is necessary to give investors certainty that a market rate of return
in the project will be achieved within a reasonable timeframe, even if
the profitability of the project has been very negatively affected. The
Inquiry proposes that the nominal interest rate in the enhanced risksharing mechanism be set at 0 percentage points and that the strike
price be increased by 20%. Since repayments are also made on the
state loans during the time the risk-sharing mechanism is active, this
means that central government is expected to recover the principal
but will miss out on interest payments during the period when the
enhanced risk sharing is active.
The annual valuations examine whether the time when the
enhanced risk-sharing mechanism is activated should be extended or
whether the unenhanced risk sharing should be reactivated. If the
34

For example, if the price of nuclear fuel at valuation is expected to increase moving forward,
which would affect future cash flows and, all else being equal, lower the value of the project
company.
35
If risk sharing has been going on for, say, three years, this means that the interest rate on
the central government loans after risk sharing will directly increase by 3*0.25=0.75
percentage points above central government’s financing cost.

51

s. 52 Kontrollera mot PDF

unenhanced risk-sharing mechanism is deemed to be sufficient for
the market value of the project company’s equity to exceed the
threshold within five years, it is to be activated and the enhanced
risk-sharing mechanism deactivated. The Inquiry assesses that
valuers are best placed to assess the expected time for the equity to
be restored. However, since two valuers appraise the value the
company, they may have different assessments of the time for the
equity to be restored, and thus different assessments of whether
enhanced risk sharing is needed or whether unenhanced risk sharing
is sufficient. The choice between unenhanced and enhanced risk
sharing should therefore be based on the average of the two valuers’
estimated times to restore the equity.

52

s. 53 Kontrollera mot PDF

Example - Risk-sharing mechanism calculation
Figure 9.10 illustrates how the risk-sharing mechanism functions
based on the previous example, i.e. a lower threshold of 35 units
and a market value of 20 units.
Figure 9.10

Risk sharing to reach the lower threshold (floor)
Normalised capital cost = 100

Note: In this illustrative example, the valuation is done in connection with commissioning. However,
the Inquiry’s proposal is that the valuation is done two years after the start of commercial
operation.

In the calculation example, at the time of valuation it is estimated
that the unenhanced risk-sharing mechanism is sufficient to
restore the market value of the equity to above the threshold
within five years. The threshold will continue to be adjusted
upwards during the period that the equity is being restored, in the
example by 2 units per year. The lower interest rate on the state
loans and the higher strike price in the CfD contribute an equity
injection of 3 units each year. After three years of the restoration
mechanism, totalling 9 units, the market value is higher than the
threshold value (44>41) and the risk sharing is terminated.

53

s. 54 Kontrollera mot PDF

Gain-sharing mechanism
If the valuation at commissioning shows that the market value of the
equity in the project company exceeds the ceiling, an gain-sharing
mechanism is activated. The gain-sharing mechanism functions in
the same way as the risk-sharing mechanism, but instead of resulting
in more favourable terms for the central government loans and the
CfD, they are tightened up. The interest rate on the central
government loans will be increased to central government’s
financing cost plus an increment of 2 percentage points and the
strike price will be reduced by 20%. The reason for a more powerful
gain-sharing mechanism than the unenhanced risk-sharing
mechanism is that the upper threshold is adjusted upwards by 15%
real rate annually. An gain-sharing mechanism that is too weak
entails a risk of no contribution from the earnings sharing. While the
earnings-sharing mechanism is active, the state loans cannot be
repaid faster than the repayment plan, as it could render the interest
component of the gain-sharing mechanism ineffective.
The gain-sharing mechanism remains active until the market
value of the project company’s equity falls below the upper
threshold. The threshold is adjusted upwards annually by 15% real
rate of return and consumer price inflation (CPI).

54

s. 55 Kontrollera mot PDF

Example - Gain-sharing mechanism calculation
Figure 9.11 illustrates how the gain-sharing mechanism works
based on previous examples, i.e. an upper threshold of 45 units
and a market value of 65 units.
Figure 9.11

Earnings sharing to reach the upper threshold (ceiling)
Normalised capital cost = 100 units

Note: In this illustrative example, the valuation is done in connection with commissioning. However,
the Inquiry’s proposal is that the valuation is done two years after the start of commercial
operation.

The gain-sharing mechanism operates in a similar way to the risksharing mechanism through amended terms and conditions for
the central government loans and the CfD. The upper threshold
will continue to be adjusted upwards during the earnings sharing.
In the example, the higher interest rate and the lower strike price
contribute in total 3 units per year. After three years, the market
value (80-9=71) falls below the upper threshold (75) and the
gains sharing is terminated.

55

s. 56 Kontrollera mot PDF

9.6

Setting the model’s parameters

The financing and risk-sharing model contains many parameters that
need to be set and regulated in loan agreements and CfDs. This
section presents the Inquiry’s approach to arriving at the proposed
parameter values presented in the previous sections.
As shown in previous chapters, there are considerable
uncertainties surrounding the costs for new nuclear power. The
assumptions made about capital costs have a particularly great
impact on the expected return from the project. Other factors – such
as operating expenses, reactor availability and future electricity
prices beyond the duration of the CfD – also have an impact. In
addition, for example changes in the electricity market could give
rise to new revenues or expenses for nuclear power that could not
be included in the Inquiry’s calculations. Taking into account the
uncertainties in input data, the proposed parameter values should be
seen as the Inquiry’s assessment of reasonable benchmarks given the
assumptions made. If the Inquiry’s assumptions are deemed to differ
from what is the best assessment, the parameters in the financing
and risk-sharing model may need to be adjusted.
Ultimately, the parameter values will be determined in
negotiations between central government and investors in new
nuclear power over the contractual terms of the loan agreement and
the CfD, respectively. It is at this time that more precise cost
estimates should be available based on binding tenders from selected
suppliers.
Finally, both the model design and parameter values will need to
be justified in a future state aid investigation. It cannot be ruled out
that changes will be necessary in order for the financing and risksharing model to be approved by the European Commission.
9.6.1

Calculation model for parameter setting

In order to estimate the outcome of the parameter values in different
scenarios, the Inquiry has developed a financial calculation model
(hereinafter the ‘calculation model’). The calculation model has
three main purposes. Firstly, the calculation model has been used by
the Inquiry to produce the proposed parameter values. Secondly, the
idea is that the calculation model should be used as methodological
56

s. 57 Kontrollera mot PDF

support in future negotiations between central government and
investors in new nuclear power. Thirdly, it can be used to quantify
the outcomes of the financing and risk-sharing model in applications
for state aid. In addition, it should be noted that other Member
States used a financial model as the basis for their discussions with
the Commission. The calculation model has been developed using
Microsoft Excel and is similar to those used by, for example,
accounting firms and banks in business valuations and financial
modelling. The calculation model has been quality-assured by an
expert who is not part of the Inquiry.
9.6.2

Assumptions in the reference scenario

The project’s economy
The assumptions about the project and its expected costs follow
those in the reference scenario in Chapter 5. In addition,
assumptions have been made regarding depreciation period,
repayment period, working capital, and taxes. These are summarised
in table 9.1table 9.1. All prices and expenses are set at the 2023 price
level and need to be adjusted for the consumer price development
(CPI).
Table 9.1

Assumptions about the project economy in the reference
scenario
2023 price level

Variable

Value

Source/Explanation

Construction period

7 years

Operational life
Availability factor
Capture rate

60 years
89%
1.05

Overnight cost

SEK 80 million per MWe
evenly distributed over the
construction period
SEK 202/MWh

In the upper part of the interval
according to Energiforsk (5–8
years)
Energiforsk.
Energiforsk.
This is slightly higher than for
Sweden’s existing nuclear power
plants. See Chapter 5.
See Chapter 5.

Operating and
reinvestment expenses

Consists of several subcomponents. See Chapter 5.

57

opaginerad Kontrollera mot PDF

Variable
Depreciation time

Value
60 years

Repayment period, debt
capital
Working capital

60 years

Taxes

20.6%

0

Source/Explanation
Straight-line depreciation during
the expected life of the nuclear
power plant.
Loan repayment equal to the
assumed depreciation period.
The project company will need to
build up working capital prior to
the operational phase, such as a
stockpile of nuclear fuel.
However, it is considered to have
a limited one-off effect on the
cash flow valuation, which is
why it is set to zero for
simplicity.
Swedish corporate tax rate. Does
not take into account rules
governing limits on interest
deductions.

Source: Energiforsk, discussions with actors in the nuclear power industry and the Inquiry’s
assessments.

Exogenous variables (for the project company)
In addition to revenues and expenses in the project company,
assumptions need to be made about exogenous macroeconomic and
financial variables affecting the project company’s economy. These
are presented in table 9.2 followed by a discussion of the assumption
for each variable.
Table 9.2

Assumptions about exogenous variables
Expressed in real terms. Electricity price at 2023 price level

Variable
Risk-free interest rate
Credit risk premium during the operational
phase
Long-term market price of electricity
WACC at time of valuation
Source: The Inquiry’s assessments.

58

Value
0.5%
2%
60 öre/kWh
4%

s. 59 Kontrollera mot PDF

Risk-free interest rate
The last few years have been marked by a global upturn in inflation,
whereupon the world’s central banks, including the Riksbank,
tightened monetary policy in order to bring inflation back down to
its target level. This has meant that households and companies have
recently been faced with a higher nominal and real rate of interest.
As can be seen in figure 9.12, over a longer period of time the real
interest rate has varied strongly but trend-wise has fallen over the
past 30 years.
Figure 9.12

Real interest rates on loans with long maturities
Per cent

Source: Lundvall (2023).

A fundamental assumption in macroeconomic theory is that central
banks can influence the real interest rate in the short term, while in
the longer term it is steered by structural factors. Before the inflation
and interest rate rises of recent years, trend-wise the real interest rate
on government bonds had been declining for several decades. The
real interest rate that is associated with normal resource utilisation
is called the neutral rate of interest. Somewhat simplified, it can be
interpreted as the interest rate that neither tightens up nor

59

s. 60 Kontrollera mot PDF

stimulates the economy, and the rate around which the Riksbank’s
policy rate will vary. The neutral rate of interest cannot be observed
and therefore needs to be derived using statistical methods and
economic theory.
While there is relatively broad consensus on the factors that
affect the neutral rate of interest, there are differences in opinion
about the level. Some analysts say that the current interest rates are
a temporary shock and that the factors that have previously been
acting to push the neutral rate down will once again predominate.
Others say that we are facing a structural shift and that permanently
higher interest rates are to be expected. An appendix to the 2023
Long Term Planning Commission Report includes estimates of the
neutral rates in the USA and the euro area for the years 1990 and
2015 (or later), which are presented in table 9.3.
Table 9.3

Empirical estimates of the trend level in the neutral rate of
interest
Per cent

Estimates of the global, equilibrium real interest
rate
El Negro et al. (2019)
Hamilton et al. (2016)
Kuvshinov and Zimmermann (2021)
Estimates of the neutral rate of interest in the euro
area and the USA according to the Holston et al.’s
method (2017)
USA
Euro area

1990

2015 or later

2.4
1.8
3.1

0.2
0.3
-0.1

3.6
2.5

0.6
0.2

Source: Lundvall (2023).

As noted in the Report, different methods and data samples give
different results, but the estimates indicate a trend level that in 2015
was close to 0%. In 2017, the Riksbank estimated that the long-term
nominal policy rate would be in the interval 2.5–4.0%,
corresponding to a real policy rate of 0.5–2.0%, provided the
inflation target is met. In recent communications, the Riksbank has
stated that the level is probably in the lower part of, or slightly

60

s. 61 Kontrollera mot PDF

below, the interval communicated in 2017. This corresponds to a real
neutral rate close to, or just under, 0.5%.
Another approach to assessing long-term interest rates is to take
into account forward-looking expectations from market participants
and the pricing in financial markets. According to Prospera’s survey
and the pricing of Swedish government bonds, expected interest
rates for longer maturities have fallen since the global financial crisis,
but have increased since the upturn in inflation in 2022. During the
period shown in figure 9.13, these expectations have corresponded
to a real rate in the interval -1% to 2% and the most recent estimate
is just under 0.5%.
Figure 9.13

Market pricing and expectations looking 5–10 years ahead
Per cent

Source: Riksbank (2024).

All in all, the Inquiry assesses that a reasonable assumption is that
the real risk-free rate is expected to remain in the interval 0–1%
moving forward, and assumes the midpoint of 0.5% for the reference
scenario.

61

s. 62 Kontrollera mot PDF

Credit risk premium
The credit risk premium refers to the premium on top of the riskfree rate that a bank or bond investor requires to lend to a company.
The credit risk premium is determined by multiple factors that
influence the assessment of the company’s business and financial
risks. Risk premiums for corporate bonds also vary over time
depending on risk sentiment and the potential return on other
assets. Based on discussions with market participants and the pricing
of corporate bonds for the major European energy companies, the
Inquiry considers that the credit risk premium for the project
company after commissioning is likely to be in the interval 1–3
percentage points above the risk-free rate. As an assumption, the
midpoint in the interval is set as 2 percentage points.36
The market price of electricity
Since the CfD will not be valid for the entire expected operational
life of the nuclear power plant, it is necessary to make assumptions
about the average market price after the hedging arrangement’s
expiry. The market price has an impact on the project company’s
revenues and thus the return in the project company.37
Svenska kraftnät’s long-term market analysis (LMA) is published
every two years and presents scenarios for the Nordic and Northern
European power systems leading up to 2045. The analysis is based
on simulations in different scenarios and thus does not constitute a
forecast of the most likely price development. The LMA presents
four scenarios38 that differ in terms of, among other things,
electricity production, electricity use, and the share of production
from different types of generation. For each scenario, the LMA
shows simulated annual average prices for each bidding zone
(figure 9.14).

36

The credit risk premium is assessed on the basis of the assumption that the project company
finances itself directly on the market without guarantees from the owner companies.
37
However, not as important as the strike price in the CfD because market revenues arise over
40 years later than the investment decision and are heavily discounted.
38
Small-scale renewable (SF), mixed roadmaps (FM), Plannable Electrification (EP) and
Renewable Electrification (EF).

62

s. 63 Kontrollera mot PDF

Figure 9.14

Simulated annual average prices in different scenarios

Source: Svenska kraftnät (2024).

The Inquiry assesses that a reasonable starting point is to consider
the scenarios for plannable electrification (EP) and mixed roadmaps
(FM). In the EP scenario, electricity consumption will increase
strongly, corresponding to 340 TWh in 2045, where 110 TWh comes
from nuclear power. In the FM scenario, production will increase to
250 TWh with 58 TWh from nuclear power. The scenarios have in
common that they require industrial investments in northern
Sweden that will even out the differences between bidding zones
compared to today. The other two scenarios, SF and EF, mean that
no new nuclear power will be built, which makes them less relevant.
A straight average of all bidding zones in the EP and FM
scenarios for 204539 gives a value of EUR 54/MWh. With an
exchange rate of SEK 11 to EUR 140, this corresponds to
approximately 60 öre/kWh, which has been assigned as the
assumption in the reference scenario.

39

Given that new nuclear power is commissioned in 2035, the CfD will not expire until 2075.
However, the Inquiry has not been able to identify scenarios with a longer time horizon than
to 2045.
40
In line with the National Institute of Economic Research’s average scenario for EUR/SEK
for the period 2024–2033.

63

s. 64 Kontrollera mot PDF

WACC at the time of valuation of the project company
The risk- and gain-sharing mechanism is based on the outcome of
market valuations of the project company. To be able to analyse in
advance the outcomes of different parameter choices, an assessment
needs to be made of which required return assumptions will form
the basis for the future valuation of the project company. The first
valuation of the project company will occur two years after the start
of commercial operation, i.e. at the earliest at the end of the 2030s.
The Inquiry’s assumptions should therefore be seen as a rough
estimate. Furthermore, the Inquiry wishes to point out that what is
said below should not be interpreted as the Inquiry setting a
framework in advance for what assumptions should form the basis
for the valuation. The valuation should be done independently of
both central government and the project company and be based on
the valuer’s best appraisal at the time of valuation. The Inquiry
assesses that a reasonable assumption for real WACC for the
completed project company is approximately 4% (see the following
Article section).
Article – Estimate of WACC using the CAPM
In order to estimate the market value of a company in the absence
of an actual transaction in which the shares change hands, the
required return on the equity and debt capital need to be
estimated. The most commonly used method for estimating
return on equity is the Capital Asset Pricing Model (CAPM).
Along with assumptions regarding the cost of debt capital and the
capital structure, the weighted average cost of capital (WACC)
can be written as
𝐸
𝐷
𝑊𝐴𝐶𝐶 =
𝑟𝑒 +
𝑟 (1 − 𝑡)
𝐷+𝐸
𝐷+𝐸 𝑑
where E and D are the proportions of equity capital and debt
capital respectively, re is the return on equity, rd is the return on
debt capital, and t is the corporate tax. Table 9.4 Presents the
Inquiry’s indicative assessment of real WACC at the time of
valuation followed by a discussion of the assumptions for the
included variables. The assessment concerns a project company
with a commissioned reactor, where uncertainties and thus

64

s. 65 Kontrollera mot PDF

required returns have decreased compared to the construction
phase.
Table 9.4

Indicative assessment of WACC for the project company with
commissioned reactor

Variable
Proportion of equity
capital (E)
Proportion of debt
capital (D)
Debt-equity ratio
(D/E)
Asset beta
Equity beta
Nominal risk-free
interest rate
Market risk
premium
Company-specific
premium
Nominal cost of
equity
Credit risk premium
Tax rate
Nominal cost, debt
capital after tax
Nominal WACC
Real WACC

Assumed interval
(min–max)
25–75%

Midpoint

25–75%

50%

95% confidence
interval

50%

1.0

0.4–2.8

0.6–2.0

2.0–3.0%

0.5
1.0
2.5%

5.5–6.5%

6.0%

0%

0%

0.4–0.6

1.0–3.0%
20.6%

8.5%

6.0–14.6%

2%
20.6%
3.6%

2.6–4.5%

6.1%
4.0%

5.0–7.1%
3.0–5%

Note: 100 000 simulated outcomes from independent continuous uniform distributions. Real return
is calculated using the Fisher equation, (1+r)/(1+i)-1, where r is the nominal return and i is the
expected inflation, assumed to be 2%.

Proportions of debt capital and equity capital
The financing and risk-sharing model means that the project
company can finance itself with 75% debt capital issued by the
Debt Office. It cannot be guaranteed that the project company
will be able to maintain the same capital structure when the state
loans are phased out and replaced by market financing. All else
being equal, a lower proportion of debt capital will cause the
65

s. 66 Kontrollera mot PDF

return on equity to decrease compared to during the construction
phase. Based on the capital structures of companies comparable to
the major Nordic energy companies, the Inquiry assesses that a
reasonable assumption is half debt and half equity for the project
company during the operational phase. Around the assumed
midpoint of 50%, the value varies within the range of 25% to 75%.
It should be noted that assuming a higher proportion of debt
capital has a limited impact on the WACC calculation as the
required return on equity can be expected to increase with higher
leverage.41
Beta values
Beta measures the correlation between a company’s return and its
return on the share market and is a key component of CAPM.
According to the CAPM, investors in a company whose returns
co-vary perfectly with the market (beta=1) will have the same
required return as the expected return on the share market. A
company with a beta lower than 1 commands a lower required
return than the market because it offers investors a diversification
of their existing portfolios. The opposite applies to a beta above
1. In the valuation context, beta is usually determined on the basis
of a sample of comparable listed companies for which beta can be
estimated empirically.
In practice, the beta applied in calculations of required return
using the CAPM is arrived at in two steps. As companies differ in
their capital structure, an adjustment is first made to remove the
effect of indebtedness in order to make the companies
comparable, which provides a value for the asset beta. Based on
recent assessments of companies in the energy sector known to
the Inquiry, the asset beta is estimated to be around 0.5 with an
interval of 0.4–0.642. In a second step, an adjustment is made for
the assumed debt/equity ratio (D/E) that gives a value for the
41

Follows from the Modigliani-Miller theorem, which has an effect in practice in that the value
of the share beta, and thus the required return on equity, increases with the company’s
indebtedness.
42
In the Czech Republic’s state aid notification, the estimated value of the asset beta was
within the interval 0.4–0.55. Other analysts are of the opinion that investments in nuclear
power and other fossil-free energy can be assumed to have a very low, or even negative, beta.
See OECD (2022), Minimising the Cost of Capital.

66

s. 67 Kontrollera mot PDF

equity beta. There is a plethora of methods for how the
adjustment should be done to go from asset beta to equity beta.43
Here a simple and in practice common approach has been chosen,
which means that the equity beta is calculated as the asset
beta*(1+D/E).
Market risk premium
The market risk premium is the additional return beyond the riskfree rate that investors require to take on the higher risk of
investing in the share market, compared to a risk-free investment.
An assessment can be made either from historical data on the
actual risk premium (ex-post) or through surveys where investors
determine the expected future risk premium (ex-ante). The most
commonly used source for market risk premium estimates for the
Swedish share market is PwC’s risk premia study. The study is
based on questionnaire responses from market participants about
their expected (ex-ante) market risk premium. The nominal
market risk premium in the 2024 study amounts to 6.1% but has
varied greatly since the study was first published in 1998. The
Inquiry assesses that it reasonable to base the assumption on the
average over a longer period of time. Following the global
financial crisis of 2007–2008, after which a level shift in the market
risk premium can be observed, according to the study the market
risk premium has amounted to approximately 6%. This level is
the midpoint in the assumed interval 5.5–6.5 %.
Company-specific risk premium
According to a number of empirical studies, a supplement needs
to be added to the required return that can be derived using the
CAPM. The most common is a size-related risk premium to take
into account that investors typically require a higher return to
invest in smaller listed companies. PwC’s risk premia study
estimates such a supplement for companies with a market
capitalisation below SEK 5 billion. The anticipated size of the
43

See Fernandez (2008) Levered and unlevered beta for a briefing on different methods for
calculating share beta.

67

s. 68 Kontrollera mot PDF

project company is greater than this, which is why a size-related
risk premium supplement is not deemed to be justified. A related
question is whether a supplement to the market risk premium is
justified in order to take into account specific risks associated
with investments in new nuclear power. On the one hand, it can
be argued that uncertainty is higher during the operational phase
of nuclear power projects compared to other projects. For
example, there is a risk that future safety requirements, taxes or
charges may impair the profitability of the project. On the other
hand, the hedging arrangement means that the revenue side is
safeguarded for 40 years, which means a significantly lower
market risk than for other projects. All in all, the Inquiry assesses
that it is reasonable to assume that the company-specific risk
premium is zero.44
Risk-free interest rate and credit risk premiums
Assumptions about risk-free interest rates and credit risk
premiums follow those made in previous sections.
The resulting real WACC
Based on assumed intervals for each variable above, the Inquiry
simulated possible outcomes for real WACC. All variables are
assumed to follow a continuous uniform distribution45 with
minimum and maximum values set as the endpoints in the
assumed intervals. The variables are assumed to be independent of
each other. The resulting distribution for real WACC shows a
roughly normal distribution, with an average of 4.0% and a
standard deviation of around 0.5%. This means that 95% of the
outcome values are within the interval 3–5% real WACC and 68%
of the outcome values are within the interval 3.5–4.5% real
WACC.
44

The Czech Republic’s state aid notification assumed a nuclear-power-specific risk premium
that the European Commission questioned in light of the aid measures in the form of central
government loans and hedging arrangements.
45
Also called a rectangular distribution, which means that all values in the assumed interval
are equally likely to occur. The Inquiry considers this to be a reasonable assumption in the
absence of empirical data which shows that certain values in the sample space are more likely.

68

s. 69 Kontrollera mot PDF

9.6.3

Parameter setting for state loans

The purpose of central government loans during the construction
phase is to obtain a lower weighted cost of capital for investments in
new nuclear power. This is made possible partly through a capital
structure with a higher proportion of debt capital, and partly
through more favourable interest rates than the market can offer
during the construction phase. The interest rate on the central
government loans is increased in increments during the operational
phase to provide an incentive to replace the central government
loans with market financing. Table 9.5 summarises the Inquiry’s
proposed parameter values for state loans.
Table 9.5

The Inquiry’s proposed parameter values for state loans

Parameter

Name Value

Capital structure
Ceiling on the project’s
framework loan

D, E
T

Risk-free interest rate

r

Increase in the interest p
premium for central
government loans in the
operational phase
Ceiling on interest
P
premium for central
government loans
Time before the interest p/P
premium ceiling is
reached

75% debt capital, 25% equity capital.
The framework loan includes a reserve for cost overruns
up to 100%, provided that the owners contribute the 25%
equity needed to maintain the capital structure.
The interest rate at the time that corresponds to central
government’s financing cost for the chosen maturity.
0.25 percentage points per year starting two years after
the start of commercial operation

4 percentage points

16 years

Note: * If central government’s financing cost is below 0% nominal interest rate in a scenario for
enhanced risk sharing, that interest rate applies instead.

As discussed in Section 9.5.1 the capital structure is a balance
between achieving a lower weighted cost of capital and central
government’s risk-taking in the project. Too low a proportion of
equity capital may give rise to excessive risk-taking in the project
because negative outcomes have a limited impact on the
shareholders (moral hazard). Too high a proportion of equity capital
may prove challenging to finance with the project owners’ existing

69

s. 70 Kontrollera mot PDF

investment budget. This may mean that injections of equity in the
project company to a large extent need to be financed by borrowing
on the market, which can affect the project owners’ credit rating and
the borrowing cost for their other activities.
In the reference scenario, the Inquiry’s proposal of a 25%
proportion of equity capital entails total investments of
SEK 25 billion for a large-scale reactor with 1 250 MWe installed
generator capacity. Given a construction period of 7 years, this
means an average annual investment need of SEK 3.6 billion. The
Inquiry considers it likely that investors, whether the investment is
for large-scale reactors or small modular reactors, will want to invest
in more than 1 250 Mwe in order to realise economies of scale and
learning effects. In addition, project owners need to ensure that they
have scope to be able to inject equity even in cost-overrun scenarios,
further increasing their potential engagement. It is possible to have
multiple owners of the project company, which reduces the
engagement for each individual owner. The sensitivity analysis in the
following section presents the estimated investment need for a
variety of proportions of equity capital, project size and cost
overruns.
Ultimately, the capital structure is a political position on what is
considered an acceptable level of risk-taking when investing in new
nuclear power. There is nothing in the structure of the model that
prevents a higher proportion of debt capital or arrangements similar
to those used in the Czech financing model.46
The gradual increase in the interest rate on central government
loans in the operational phase is also a balance between obtaining a
lower cost of capital over a longer period and the point in time for
phasing out central government’s engagements in the projects. The
Inquiry assesses that a rate of increase corresponding to
0.25 percentage points per year provides a reasonable balance. With
the reference scenario assuming a credit risk premium for the project
company after reactor commissioning corresponding to
2 percentage points, this means that the state loans are expected to

46

In the Czech Republic, the proportion of equity capital is very low in the expected scenario
– around 2%. However, conditional equity capital is reserved that can be used to finance the
project in the event of cost overruns.

70

s. 71 Kontrollera mot PDF

be replaced by market financing ten years after the start of
commercial operation.47
Sensitivity analysis
Table 9.6 illustrates how the average annual need for investments in
equity capital is affected by the proportions of debt capital and
equity capital, the project size, and cost overruns.
Table 9.6

Annual investments in equity capital for a variety of capital
structures, project sizes and cost overruns
SEK billion at 2023 price level

Project size and proportion
of equity capital
Equivalent to a large-scale
reactor (1 250 MWe)
According to budget
50% cost overrun
100% cost overrun
Equivalent of two largescale reactors (2 500 MWe)
According to budget
50% cost overrun
100% cost overrun

5% equity
capital

10% equity
capital

25% equity
capital

50% equity
capital

0.7
1.1
1.4

1.4
2.1
2.9

3.6
5.4
7.1

7.1
10.7
14.3

1.4
2.1
2.9

2.9
4.3
5.7

7.1
10.7
14.3

14.3
21.4
28.6

Note: Assuming an evenly distributed investment need over a construction period of 7 years. The capital
cost without cost overruns according to the reference scenario’s assumption of SEK 80 million per
installed MWe.

The total need for investment of equity capital in the project
company is given above. Among other things, the individual
investor’s investment need depends on the scope for investment and
investment strategy. For example, a larger energy company may
want to have a majority stake in order to be able to actively manage
the project, while other investors prefer a minority stake. Based on
discussions with actors in the nuclear power industry, the Inquiry
47

8 years after the phase-in, which starts 2 years after the start of commercial operation.
However, if the capital structure in the operational phase entails a proportion of equity capital
higher than 25%, it may be rational for the project company to maintain the central
government loans despite an interest rate higher than the market offers in order to obtain a
lower weighted cost of capital and higher return on equity.

71

s. 72 Kontrollera mot PDF

assesses that the project company, at least during the construction
phase, will likely have a small number of strategic investors rather
than many small minority holdings.
It has not been possible for the Inquiry to make a detailed analysis
of the proportion of equity capital that is included in the investment
budget of potential investors in new nuclear power. The question is
complex and depends on how the investment in new nuclear power
affects the investor’s existing activities and its cash flows as well as
its indebtedness among other things. Depending on the project’s
size and the participating interest, investments in new nuclear power
can potentially have an impact on the credit rating of owner
companies.48 However, the Inquiry’s assessment is that the proposed
25% proportion of equity capital should be consistent with a larger
energy company going in with a majority stake in the project
company. A more detailed analysis of the capital structure and its
impact on the individual investor’s existing activities will be
necessary at a later stage, based on the individual project’s
conditions.
9.6.4

Parameter setting for CfD

The starting point for parameter setting in the CfD is to give the
project company’s owners a sufficiently high return on equity to
bring about investments in new nuclear power. The Inquiry’s
assessment is that this means a strike price that is above the expected
electricity price. The fact that the strike price is higher than indicated
in scenario analyses of future electricity prices can be socioeconomically justified by the external benefits that are not fully
reflected in today’s price signals. Table 9.7 summarises the Inquiry’s
proposed parameter values for the CfD.

48

Among other things, the rating agencies weigh in financial metrics such as the ratios
FFO/Debt and Debt/EBITDA, which are negatively affected during the construction phase
when on the one hand the nuclear power project does not contribute operational cash flows
and on the other has higher indebtedness.

72

s. 73 Kontrollera mot PDF

Table 9.7

The Inquiry’s proposed parameter values for the CfD

Parameter

Name

Value

Strike price
Duration

X
Y

Entry into force
Reference capacity

Z
Q

80 öre/kWh at 2023 price level
40 years from the planned start of
commercial operation
At the start of commercial operation
89%1

1 Initial value, later replaced by a moving average of the capacity factor actually achieved for hours

with positive prices in the electricity market. See previous section on hedging arrangements.

Expected outcomes in the reference scenario
A key factor in an investor’s assessment of a project is the estimated
internal rate of return, IRR49, of the project. How IRR relates to
WACC is a decision criterion for the investor and determines
whether the investment will be made. If IRR falls below WACC, the
investment is not considered profitable. If there are alternative
investments with a higher IRR, all else being equal they will be
chosen over investments in new nuclear power. WACC is given by
the cost of, and the relative proportions of, debt capital and equity
capital. Given a cost (interest) for debt capital and a fixed capital
structure, WACC is determined by the required return on equity of
the project company’s owners. The required return on equity is
unknown to all except the investor itself and is assessed in relation
to the estimated risks in the project’s cash flows, which in turn are
affected by how the investor prices the safeguards from the
financing and risk-sharing model.
In the reference scenario, the Inquiry’s proposal for a CfD with
a strike price of 80 öre/kWh and a duration of 40 years leads to a real
IRR for the project of 4% over the entire investment period. The
return on equity will vary over the investment period, depending on
the capital structure and the cost of debt capital. Provided that the
framework loan is fully utilised, the capital structure is known
during the construction phase and amounts to 75% debt capital and
25% equity capital. Given that the project company is valued based
on the assumption of a real WACC of 4.0% after the start of
49

IRR is calculated as the discount rate that, at the time of the investment decision gives a
zero net present value of the project company’s free cash flows to equity and debt capital
(FCF).

73

s. 74 Kontrollera mot PDF

commercial operation, the Inquiry calculates the expected real
return on equity during the construction phase as 12.5%.50
The expected return on equity during the operational phase will
be affected by, among other things, what an optimal capital structure
is at any given time. Given the capital structure that can be observed
for European energy companies today, it is reasonable to expect that
the proportion of equity capital in the project company will need to
be higher than 25% in order to attract market financing on
reasonable terms. In the Inquiry’s indicative WACC calculation
with an assumption of 50% debt capital, the real return on equity is
estimated at 6.5% during the operational phase. If the project
company is able to bear a higher leverage (higher than 50% debt
capital) or obtain a lower interest rate (lower than 2.5% real rate),
all else being equal this will give a higher return on equity during the
operational phase, and vice versa.
Sensitivity analyses
Sensitivity analyses of how the return on equity during the
construction phase is affected when the assumptions for input are
varied are presented below. Return on equity is calculated as follows:
1. The assumptions in the reference scenario are varied, for example
with regard to the construction cost.
2. A cash flow valuation is done using the calculation model to
estimate the value of the equity in the project company given
assumptions about revenues, expenses and WACC at the time of
valuation.
3. Return on equity is calculated by means of iterative target
augmentation until the invested equity in the project company
amounts to the estimated market value on the valuation date.
The returns shown below refer to the return obtained without the
risk- or gain-sharing mechanism being activated. In cases where the
50

The calculated return corresponds to the return that would be received if the owners could
dispose of the shares in the project company at the estimated market value at the time of
valuation. Alternatively, the shares are retained and the corresponding return is instead
realised over time by sharing in future earnings (and dividends) with the same net present
value as the market value.

74

s. 75 Kontrollera mot PDF

return falls outside the return interval given by the lower and upper
thresholds, the risk- or gain-sharing mechanism will be activated.
These outcomes are highlighted in the sensitivity analysis and
described in more detail in later sections that specifically analyse the
risk- and earnings-sharing mechanism.
Strike price and duration of the CfD
Table 9.8 illustrates how the return on equity up until the valuation
date is affected by different parameter choices for strike price and
duration in the CfD.
Table 9.8

Expected real return on equity up until the valuation date for
different durations and strike prices
Percentage annual return on equity

Duration and
strike price
30 years
40 years
50 years

60 öre per kWh 70 öre per kWh 80 öre per kWh 90 öre per kWh
-12.7%1
-12.7%1
-12.7 %1

2.0%
3.4%
4.4%

10.5%
12.5%
13.7%

16.6%2
18.8%2
20.2 %2

1 Risk-sharing mechanism activated.
2 Gain-sharing mechanism activated.

With the proposed parameter values (80 öre/kWh for 40 years), the
expected return on equity in the reference scenario is calculated at
12.5%. The return is sensitive to fluctuations in the strike price,
which is explained by a large change in revenue with unchanged
costs. For a large-scale reactor with installed generator capacity of
1 250 MW with 89% availability, an increase in the strike price
of 10 öre/kWh corresponds to an increase in revenue of
approximately SEK 1 billion per year. The return is less sensitive to
the choice of duration, which is because cash flows beyond 30 years
after commissioning are strongly discounted.

75

s. 76 Kontrollera mot PDF

Delays and cost overruns
Table 9.9 illustrates how the return on equity up until the valuation
date is affected by cost overruns and delays compared to the
reference scenario.
Table 9.9

Expected real return on equity up until the valuation date in the
case of time and cost overruns
Percentage annual return on equity

Delays and cost
overruns

-25%

0%

25%

50%

-2 years
0 years
2 years
4 years

33.3%2
25.1%2
20.0%2
16.5%2

16.5%2
12.5%
9.8%
8.0%

-0.8%1
-1.4%1
-1.8%1
-2.1%1

-24.3%1
-22.1%1
-20.9%1
-20.4%1

1 Risk-sharing mechanism activated.
2 Gain-sharing mechanism activated.

As a result of the high fixed capital costs for new nuclear power,
returns are sensitive even to relatively modest deviations from the
reference scenario. The project company thus has strong incentives
to keep to schedule and the budget to obtain a higher return than
the return given by the lower threshold.51
All else being equal, the proposed parameters for the CfD can
accommodate a cost overrun of around 20% before the risk-sharing
mechanism is expected to activate. In view of the cost overruns of
recent European nuclear power projects, it cannot be ruled out that
the risk-sharing mechanism will have to be activated. One way to
reduce the likelihood of risk sharing being activated is to raise the
strike price in the CfD. For example, a strike price of 90 öre/kWh
would mean that, all else being equal, a cost overrun of just over 35%
could be accommodated before risk sharing is activated.52 The strike
price in the CfD is thus a balance between the probability of risk or
51

The effect of late payments on the return up until the valuation date depends on several
factors, in particular the interest rate on the central government loans. In the calculation
example with a 50% cost overrun, the average annual return in the case of delays improves,
while the accumulated return is lower as a result of more years of negative returns. At higher
interest rate levels, delays become more costly. With a real interest rate on the central
government loans of 1.0 % instead of the reference scenario’s assumption of 0.5 %, the
average annual return in the case of delays decreases, even at a 50% cost overrun.
52
In all cases, the expected scenario would instead be to trigger earnings sharing.

76

s. 77 Kontrollera mot PDF

gain sharing being activated and a higher cost for electricity in the
reference scenario.
The Inquiry argues that, from the perspective of central
government and the electricity consumers, it may be rational to
accept a relatively high risk of risk sharing being activated because,
unlike the CfD, it is temporary. In a scenario where unenhanced risk
sharing is sufficient, this would mean a 10% higher strike price,
equivalent to 88 öre/kWh, over a five-year period. If enhanced risk
sharing is required, this means a 20% higher strike price
(96 öre/kWh), but still for a limited period.53 However, a higher
agreed strike price in the CfD is guaranteed to last for 40 years,
which risks being an expensive way to insure against cost overruns.
Additionally, it should be taken into account that the cost
overrun percentages observable from previous nuclear projects are
based on investment budgets that have greatly underestimated the
costs. Given the lessons learned from these projects, the Inquiry
assesses that the expected costs that form the basis for the
application to participate in the financing and risk-sharing
programme should be unbiased estimates of expected value.54
Variations in operating expenses
Table 9.10 illustrates how the return on equity up until the valuation
date is affected by estimated higher expected costs at the time of
valuation.
Table 9.10

Expected real return on equity up until the valuation date for
different operating expenses assumptions
Percentage annual return on equity

Operating expenses
Return on equity

-25%
16.1%1

0%
12.5%

25%
8.1%

50%
2.5%

1 Gain-sharing mechanism activated.

53

See later sections on sensitivity analyses for the risk-sharing mechanism which show that
enhanced risk sharing is expected to restore the equity to above the threshold much earlier
than the expiry date of the CfD.
54
In addition, the risk-sharing mechanism provides the project company with an incentive to
provide its best appraisal of expected costs, as cost overruns above 50% result in a lower return
in the list of the lower threshold.

77

s. 78 Kontrollera mot PDF

As shown in the Table, all other things being equal, there are
relatively large increases in operating expenses compared to the
reference scenario without the risk-sharing mechanism being
activated.
WACC assumed in the valuation
Table 9.11 illustrates how the estimated return on equity up until the
valuation date is affected by the WACC assumptions made during
the operational phase which form the basis for the valuation.
Table 9.11

Expected real return on equity up until the valuation date for
different WACC assumptions
Percentage annual return on equity

WACC on the valuation date
Return on equity

3.0%

3.5%

4.0%

4.5%

5.0%

20.8%1

16.7%1

12.5%

8.0%

3.2%

1 Risk-sharing mechanism activated.

A valuation is inevitably uncertain, particularly with regard to the
discount rate (WACC) applied. According to the Inquiry’s
indicative assessment, it is reasonable to expect that a real WACC
will very probably lie within half a percentage point of the previously
estimated value (3.5–4.5%) and with very high probability within
one percentage point (3.0–5.0%). All other things being equal, the
Inquiry therefore considers it unlikely that the risk-sharing
mechanism will be triggered due to a higher than expected WACC
at the time of valuation. Since the proposed strike price yields an
expected rate of return that lies relatively close to the upper
threshold, it is more likely to trigger earnings sharing than risk
sharing.
Risk-free rate
Table 9.12 illustrates how the return on equity up until the valuation
date is affected by variations in the risk-free rate. Two scenarios are
calculated: one with a temporarily higher or lower interest rate

78

s. 79 Kontrollera mot PDF

during the construction phase; and one where the risk-free rate level
is deemed to have permanently changed.55
Table 9.12

Real return on equity up until the valuation date for different
risk-free rate assumptions
Percentage annual return on equity

Real risk-free rate
Risk-free rate during the
construction phase
Permanent shift in riskfree rate

0.0%

0.25%

0.5%

0.75%

1.0%

13.1%

12.8%

12.5%

12.1%

11.8%

17.2%1

15.3%1

12.5%

10.3%

8.1%

1 Earnings-sharing mechanism activated. In the case of a permanent change in the risk-free rate, it is

assumed that the specified rate level applies throughout the entire construction and operational
phases.

A risk-free real rate that is 0.5 percentage points higher or lower
during the construction phase has a relatively small impact on the
project’s yield. This is explained by the fact that the construction
period (7 years in the reference scenario) is short relative to the
operational life (60 years). However, if the risk-free rate is assessed
as having permanently changed at the time of valuation, it would
have a major impact on the return. This is because the anticipated
cash flows over 60 years are discounted at a lower or higher interest
rate in the valuation of the project company.
Return on equity for varying capital structures
Table 9.13 illustrates how, all else being equal, the return on equity
during the construction phase varies with different ratios of
borrowed to equity capital.

55

The difference is that the first scenario implies an unchanged WACC at the time of valuation
(as interest expenses are expected to revert to the reference scenario’s), while the second
scenario assumes a permanent shift, which is taken into account in the WACC calculation.

79

s. 80 Kontrollera mot PDF

Table 9.13

Real return on equity up until the valuation date for different
capital structure assumptions
Percentage annual return on equity

Capital structure
Return on equity

10% debt
capital
4.5%

25% debt
capital
5.2%

50% debt
capital
7.3%

75% debt
capital
12.5%

90% debt
capital
23.2%1

1 Gain-sharing mechanism activated.

With the Inquiry’s proposal of 75% debt capital during the
construction period, the expected return on equity will be 12.5%. If
a lower or high proportion were to be decided, other parameters in
the model would need to be adjusted. For example, a 90%
proportion of debt capital would result in a return that exceeds the
upper threshold in the risk- and gain-sharing mechanism. All else
being equal, this would motivate less favourable terms for the central
government loans and the CfD.
The return on equity during the operational phase depends on
what the optimal capital structure is after the transition to market
financing, which is unknown in advance. Given an unchanged
interest rate, a higher proportion of debt capital gives a higher return
on equity. At the same time, unlike with the state loans, the interest
rate that private lenders require is expected to increase where there
is a higher proportion of debt capital. The Inquiry’s reference
scenario assumes that the project company will need to have a higher
proportion of equity capital (50%) in order to replace the state loans
with market financing at the assumed interest rate (real risk-free rate
of 0.5 percentage points and a credit risk premium of 2
percentage points). With this capital structure and interest rate level,
the project company is expected to obtain a real annual return on
equity of 6.5% during the operational phase. If the project company
can bear a higher proportion of debt capital or borrow at a lower
interest rate, it will have a positive impact on the return on equity.
9.6.5

Parameter setting for risk and gain sharing

The parameters in the risk- and earnings-sharing mechanism are set
to protect investors from the worst outcomes and to give central
government and the electricity consumers an upside in the best

80

s. 81 Kontrollera mot PDF

outcomes. Relieving investors from risks during the construction
phase has a dampening effect on required returns, which leads to a
lower cost of producing electricity from new nuclear power. Table
9.14 summarises the Inquiry’s proposed parameter values for the
risk- and gain-sharing mechanism.
Table 9.14

The Inquiry’s proposed parameter values for risk and gain
sharing

Parameter

Name

Upwards adjustment of lower
threshold (floor) for risk sharing

a

Interest in unenhanced risk sharing
Interest in enhanced risk sharing
Strike price CfD in unenhanced risk
sharing
Strike price CfD in enhanced risk
sharing
Upwards adjustment of upper
threshold (ceiling) for gain sharing
Interest rate in gain-sharing
mechanism
Strike price in CfD in gain-sharing
mechanism

Value

s

2% real annual return on invested
equity
Central government’s financing cost for
the chosen maturities
0% nominally 1
10% higher than the contracted strike
price
20% higher than the contracted strike
price
15% real annual return on invested
equity
The central government financing cost
for the chosen maturities plus
2 percentage points

K

20% lower than the contracted level

r
R
l
L
v

If central government’s financing cost is below 0% nominal interest rate in a scenario for enhanced
risk sharing, that interest rate applies instead.
1

The parameter setting for the risk and gain-sharing mechanism was
based on a number of criteria and trade-offs. Firstly, the Inquiry
assesses that a wide interval between the lower and upper thresholds
is justified in order to incentivise the project owner to be efficient.
The lower threshold gives a real return in the interval -2% to 2%
depending on the size of any cost overrun.56 This removes the worst
outcomes for the project company but gives a significantly lower
return than the owners’ required return. The 15% return in the
calculation of the upper threshold allows the project company to
retain a significant portion of the earnings should the project
56

Since the financing model has a ceiling of 100% cost overruns, the return on the total
amount invested will be low but positive.

81

s. 82 Kontrollera mot PDF

outcomes be favourable. Returns exceeding this are shared with
central government and the electricity consumers through the gainsharing mechanism.
Secondly, a balance needs to be struck between a low probability
of triggering risk sharing and the risk that the terms in the CfD are
set too generously. As discussed in the previous section, the Inquiry
assesses that it may be reasonable to accept a relatively high
probability of triggering risk sharing because it lasts for a limited
time. In unenhanced risk sharing, the interest rate on the central
government loans is the same as during the construction phase and
amounts to central government’s financing cost for the chosen
maturity. The unenhanced risk sharing thus does not entail any cost
to central government. The strike price will increase by 10%, which
means that the cost of electricity produced by nuclear power will
increase by 8 öre/kWh given a strike price of 80 öre/kWh in the
CfD. The enhanced risk-sharing mechanism is much more powerful,
particularly with regard to the interest rate on the central
government loans, which is set at 0% in nominal terms. The strike
price will increase by 20%, corresponding to 16 öre/kWh. The
Inquiry argues that a powerful, enhanced risk-sharing mechanism is
necessary to give investors certainty that a market rate of return will
be achieved within a reasonable timeframe, even if the profitability
of the project has been very negatively affected. At each valuation,
an assessment is made to determine whether enhanced risk sharing
is necessary or whether unenhanced risk sharing is sufficient, which
reduces the risk of overcompensation from risk sharing.
Thirdly, the Inquiry considers that a powerful gain-sharing
mechanism is needed to provide a meaningful upside for central
government and the electricity consumer. Because the lower
threshold is adjusted upwards by 15% per year, if gains sharing is
too weak, there is a risk of not enough time passing for it to provide
any major contribution. In the gain-sharing mechanism, the interest
rate on the central government loans is 2 percentage points above
central government’s financing cost and the strike price is lowered
by 20%, corresponding to -16 öre/kWh.

82

s. 83 Kontrollera mot PDF

Expected outcomes in the reference scenario
As stated in previous sections, the expected outcome is that neither
the risk nor the gain sharing will be activated. In the reference
scenario, the real return on equity during the construction phase is
estimated to be 12.5%.
Sensitivity analysis
Sensitivity analyses are presented below for when the risk- or gainsharing mechanism is activated and for how long it is expected to
last when the input data are varied. The calculation is as follows:
1. The assumptions in the reference scenario are varied in terms of
construction cost and delays.
2. A cash flow valuation is done using the calculation model to
estimate the value of the equity in the project company given
assumptions about revenues, expenses and WACC at the time of
valuation.
3. Where the estimated value of the equity at the time of valuation
is outside the interval given by the lower and upper thresholds,
the risk- or gain-sharing mechanism is activated.
4. For the current scenario, the calculation model estimates the
number of years of (unenhanced or enhanced) risk sharing and
earnings sharing required to restore the value of the equity in the
project company to between the lower and upper thresholds.
Sensitivity analyses are done for variations in cost overruns and
delays, while all other values are kept constant. In practice, this is
likely so that these variables co-vary57 somewhat with other
variables, which is not captured by the sensitivity analysis. The
Inquiry assesses that it may be justified at a later stage to supplement
the sensitivity analysis with scenarios that combine variations of
several variables at the same time.

57

For example, a cost overrun during the construction phase could be due to a general price
increase on input factors in the nuclear power industry that also affect operating expenses.

83

s. 84 Kontrollera mot PDF

Delays and cost overruns
Table 9.15 illustrates in which scenarios the risk- or gain-sharing
mechanism is activated and how long it is expected to last for
variations in delays and cost overruns compared to the reference
scenario. Some simplifications have been made in the analysis that
need to be taken into account. Firstly, it is assumed that the total
capital costs are distributed evenly over the construction period even
in cases of cost overruns. A more likely course of events is possibly
that the project initially proceeds according to budget, but that
problems come to light some time into the construction phase at
which point costs increase. Secondly, very large cost overruns may
mean that equity in the project company, based on the valuation
done, is judged to be low or even negative. In accordance with the
provisions of the Swedish Annual Accounts Act and supplementary
accounting standards, a write-down test must be carried out when
there is an indication of impairment. One possible consequence of a
write-down test is that the share capital in the project company
needs to be restored through capital injections. Such factors have
not been taken into account in the sensitivity analysis.
Table 9.15

Expected time to restore the value of the equity to the risk- and
gain-sharing threshold in the case of cost overruns and delays
The number of years of risk sharing or gain sharing calculated from
the time of valuation

Delays and cost
overruns
-2 years
0 years
2 years
4 years
6 years

-25%

0%

25%

50%

100%

6 years (G)
4 years (G)
2 years (G)
1 years (G)
-

-

1 year (R)
1 year (R)
1 year (R)
2 year (R)
3 year (R)

5 years (R*)
6 years (R*)
7 years (R*)
7 years (R*)
7 years (R*)

12 years (R*)
13 years (R*)
13 years (R*)
14 years (R*)
14 years (R*)

Note: (G) means gain sharing, (R) means risk sharing and - means that neither risk sharing nor gain
sharing is necessary. (R*) means that the enhanced risk-sharing mechanism is activated during (parts
of) the period.

Firstly, it can be noted that the unenhanced risk-sharing mechanism
is expected to be sufficient to handle cost overruns of 25% within
three years of the valuation date. For cost overruns of 50% with
varying degrees of delays, the enhanced risk-sharing mechanism is

84

s. 85 Kontrollera mot PDF

required for parts of the period, but a restoration to within the
thresholds is expected within a period of 5–7 years from the
valuation date. For very large cost overruns corresponding to 100%
above the expected costs, 14 years of risk sharing would be required,
with the majority of the period under enhanced risk sharing. 58 It
should also be noted here that the number of years of risk sharing
refers to years from the initial valuation, which means that scenarios
with delays entail a longer period of low returns for the project
company’s owners. The example with a 100% cost overrun and a 6year delay means that the project company is expected to exit the
risk-sharing phase 29 years after the start of construction.59
In light of the simplified assumptions made, the analysis should
be seen as indicative. However, one conclusion is that the risksharing mechanism is expected to be powerful enough to give the
project company a low but positive return even in scenarios with
significant cost overruns and delays.

58

That the overall expected risk-sharing period is in some cases constant for varying degrees
of delay is explained by the enhanced risk sharing being activated for a larger portion of the
period in the case of longer delays, but with a retained constant risk-sharing period. For cases
with over 50% cost overruns, the surplus portion gets a negative return (according to the
proposal, -2% real rate). This has a certain dampening effect on the time to restore the value
of the equity in the case of larger cost overruns because the threshold is not adjusted upwards
as quickly.
59
Because the valuation is done 2 years after commissioning, which falls 13 years (7+6) after
the start of construction and the risk sharing lasts for 14 years after the valuation.

85