MLAKYTA AND ELPRAM, S.R.O. AND EUROFINANZ, S.R.O. v. SLOVAKIA
30 april 2020 · nr 43917/19 · nr 43977/19 · ECLI:CE:ECHR:2020:0430DEC004391719
Så kom texten hit
- Källa: Europadomstolen (HUDOC), © ECHR-CEDH · dokumentet i HUDOC
- Text: domstolens egen text på engelska, utläst ur HUDOC:s HTML. Styckenumren är domens; varje stycke har en egen adress (#p1, #p2 …).
- Hämtad hit: 14 november 2026
- Villkor: Domstolens texter återges med källan angiven (© ECHR-CEDH), avgiftsfritt och i informationssyfte, enligt domstolens villkor (echr.coe.int, Copyright and Disclaimer). Den elektroniska versionen ges ut enligt artikel 44.3 i konventionen; den undertecknade texten i domstolens arkiv är den autentiska. Icke-officiella översättningar i HUDOC är skyddade av upphovsrätt och står här bara som länk.
Uppgifter ur HUDOC
- Artiklar: Artikel 6; Artikel 39;
- Slutsats: Struck out of the list
- Betydelse enligt domstolen: nivå 4 (liten betydelse)
- Målet: alla dokument och språkversioner (1)
Citera
Europadomstolens beslut den 30 april 2020 i målet MLAKYTA AND ELPRAM, S.R.O. AND EUROFINANZ, S.R.O. mot Slovakien (nr 43917/19 och 43977/19)
Domstolens text
THIRD SECTION
DECISION
Applications nos. 43917/19 and 43977/19
Vladimir MLAKYTA and ELPRAM, S.R.O.
against Slovakia
and EUROFINANZ, S.R.O. against Slovakia
The European Court of Human Rights (Third Section), sitting on 30 April 2020 as a Committee composed of:
Dmitry Dedov, President,
Alena Poláčková,
Gilberto Felici, judges,
and Liv Tigerstedt, Acting Deputy Section Registrar,
Having regard to the above applications lodged on the various dates indicated in the appended table,
Having regard to the formal declarations accepting a friendly settlement of the cases,
Having deliberated, decides as follows:
FACTS AND PROCEDURE
The list of applicants is set out in the appended table.
The applicants’ complaints under Article 6 § 1 of the Convention concerning the excessive length of civil proceedings were communicated to the Slovak Government (“the Government”).
The Court received friendly-settlement declarations under which the applicants agreed to waive any further claims against Slovakia in respect of the facts giving rise to these applications, subject to an undertaking by the Government to pay them the amounts detailed in the appended table. These amounts will be payable within three months from the date of notification of the Court’s decision. In the event of failure to pay these amounts within the above-mentioned three-month period, the Government undertake to pay simple interest on them, from the expiry of that period until settlement, at a rate equal to the marginal lending rate of the European Central Bank during the default period plus three percentage points.
The payment will constitute the final resolution of the cases.
THE LAW
Having regard to the similar subject matter of the applications, the Court finds it appropriate to examine them jointly in a single decision.
The Court takes note of the friendly settlement reached between the parties. It is satisfied that the settlement is based on respect for human rights as defined in the Convention and the Protocols thereto and finds no reasons to justify a continued examination of the applications.
In view of the above, it is appropriate to strike the cases out of the list.
For these reasons, the Court, unanimously,
Decides to join the applications;
Decides to strike the applications out of its list of cases in accordance with Article 39 of the Convention.
Done in English and notified in writing on 22 May 2020.
Liv Tigerstedt Dmitry Dedov
Acting Deputy Registrar President
APPENDIX
List of applications raising complaints under Article 6 § 1 of the Convention
(excessive length of civil proceedings)
| No. | Application no. Date of introduction | Applicant’s name Date of birth / Date of registration | Representative’s name and location | Date of receipt of Government’s declaration | Date of receipt of Applicant’s declaration | Amount awarded for pecuniary and non-pecuniary damage per applicant/household (in euros)[1] | Amount awarded for costs and expenses per application (in euros)[2] |
| 43917/19 12/08/2019 | Household Vladimir MLAKYTA 04/06/1963 ELPRAM, S.R.O. 11/07/2003 | Martin Dočár Bratislava | 25/03/2020 | 21/01/2020 | 2,600 | 250 | |
| 43977/19 09/08/2019 | EUROFINANZ, S.R.O. 12/11/2003 | Martin Burian Žilina | 25/03/2020 | 30/01/2020 | 5,200 | 250 |
Målets dokument (1)
- Beslut, 30 april 2020 (denna sida) · engelska