Caleffi v. Italy
24 maj 1991 · nr 11890/85
Så kom texten hit
- Källa: Europadomstolen (HUDOC), © ECHR-CEDH · dokumentet i HUDOC
- Text: domstolens egen text på engelska, utläst ur HUDOC:s HTML. Styckenumren är domens; varje stycke har en egen adress (#p1, #p2 …).
- Hämtad hit: 14 november 2026
- Villkor: Domstolens texter återges med källan angiven (© ECHR-CEDH), avgiftsfritt och i informationssyfte, enligt domstolens villkor (echr.coe.int, Copyright and Disclaimer). Den elektroniska versionen ges ut enligt artikel 44.3 i konventionen; den undertecknade texten i domstolens arkiv är den autentiska. Icke-officiella översättningar i HUDOC är skyddade av upphovsrätt och står här bara som länk.
Uppgifter ur HUDOC
- Artiklar: Artikel 6; Artikel 41;
- Slutsats: Violation of Art. 6-1;Non-pecuniary damage - financial award;Costs and expenses award - Convention proceedings;Lack of jurisdiction (measures to remedy the situation)
- Betydelse enligt domstolen: nivå 4 (liten betydelse)
- Målet: alla dokument och språkversioner (2)
Citera
Europadomstolens sammanfattning av avgörandet den 24 maj 1991 i målet Caleffi mot Italien (nr 11890/85)
Domstolens text
Information Note on the Court’s case-law No.
May 1991
Caleffi v. Italy - 11890/85
Judgment 24.5.1991
Article 6
Article 6-1
Reasonable time
Length of civil proceedings: violation
[This summary is extracted from the Court’s official reports (Series A or Reports of Judgments and Decisions). Its formatting and structure may therefore differ from the Case-Law Information Note summaries.]
I. ARTICLE 6 § 1 OF THE CONVENTION ("reasonable time")
A. Period to be considered
Starting-point: institution of proceedings against defendant.
Close: date when friendly settlement reached.
Result: slightly more than seven years and seven months.
B. Relevant criteria
Reasonableness of length of proceedings: to be assessed in light of circumstances of case and criteria laid down in Court's case-law.
Excessive workload did not justify failure – especially in the cassation proceedings – to comply with shortened time-limits applicable to employment cases.
Conclusion: violation (unanimously).
II. ARTICLE 50 OF THE CONVENTION
A. Non-pecuniary damage: compensation awarded.
B. Costs and expenses incurred before Convention organs: reimbursement.
C. Publication of judgment: Court had no jurisdiction to order Italy to do this.
Conclusion: respondent State to pay applicant specified sums (unanimously).
© Council of Europe/European Court of Human Rights
This summary by the Registry does not bind the Court.