Saccomanno v. Italy
12 maj 1999 · nr 36719/97
Så kom texten hit
- Källa: Europadomstolen (HUDOC), © ECHR-CEDH · dokumentet i HUDOC
- Text: domstolens egen text på engelska, utläst ur HUDOC:s HTML. Styckenumren är domens; varje stycke har en egen adress (#p1, #p2 …).
- Hämtad hit: 14 november 2026
- Villkor: Domstolens texter återges med källan angiven (© ECHR-CEDH), avgiftsfritt och i informationssyfte, enligt domstolens villkor (echr.coe.int, Copyright and Disclaimer). Den elektroniska versionen ges ut enligt artikel 44.3 i konventionen; den undertecknade texten i domstolens arkiv är den autentiska. Icke-officiella översättningar i HUDOC är skyddade av upphovsrätt och står här bara som länk.
Uppgifter ur HUDOC
- Artiklar: Artikel 6; Artikel 41;
- Slutsats: Violation of Art. 6-1;Pecuniary damage - claim dismissed;Non-pecuniary damage - financial award;Costs and expenses partial award
- Betydelse enligt domstolen: nivå 4 (liten betydelse)
- Målet: alla dokument och språkversioner (2)
Citera
Europadomstolens sammanfattning av avgörandet den 12 maj 1999 i målet Saccomanno mot Italien (nr 36719/97)
Domstolens text
Information Note on the Court’s case-law 6
May 1999
Saccomanno v. Italy - 36719/97
Judgment 12.5.1999 [Section II]
Article 6
Criminal proceedings
Article 6-1
Reasonable time
Length of criminal proceedings: violation
In 1990 the applicant was charged with malicious accusation. Eventually, in 1997, he was acquitted on the ground that no offence had been made out. He complained of the length of the proceedings. The period to be taken into account was more than six years and four months for a single level of jurisdiction.
Law: The Court noted that the case had not been complex and that although some of the delays could be laid at the applicant’s door, that did not justify the length of the intervals between hearings, nor, above all, the overall length of the proceedings. There had been several long periods of inactivity for which the Italian judicial authorities had been responsible and in respect of which the Government had advanced no possible explanation.
Conclusion: violation (unanimous).
Article 41: The Court awarded the applicant ITL 10,000,000 for non-pecuniary damage and ITL 1,500,000 for costs and expenses, but dismissed his claims in respect of pecuniary damage as it found no causal link between the violation of Article 6 § 1 and the economic loss claimed.
© Council of Europe/European Court of Human Rights
This summary by the Registry does not bind the Court.