Bosio and Moretti v. Italy
6 september 1999 · nr 36608/97
Så kom texten hit
- Källa: Europadomstolen (HUDOC), © ECHR-CEDH · dokumentet i HUDOC
- Text: domstolens egen text på engelska, utläst ur HUDOC:s HTML. Styckenumren är domens; varje stycke har en egen adress (#p1, #p2 …).
- Hämtad hit: 14 november 2026
- Villkor: Domstolens texter återges med källan angiven (© ECHR-CEDH), avgiftsfritt och i informationssyfte, enligt domstolens villkor (echr.coe.int, Copyright and Disclaimer). Den elektroniska versionen ges ut enligt artikel 44.3 i konventionen; den undertecknade texten i domstolens arkiv är den autentiska. Icke-officiella översättningar i HUDOC är skyddade av upphovsrätt och står här bara som länk.
Uppgifter ur HUDOC
- Artiklar: Artikel 6; Artikel 41;
- Slutsats: Violation of Art. 6-1;Pecuniary damage - claim dismissed;Non-pecuniary damage - financial award;Costs and expenses partial award
- Betydelse enligt domstolen: nivå 4 (liten betydelse)
- Målet: alla dokument och språkversioner (2)
Citera
Europadomstolens sammanfattning av avgörandet den 6 september 1999 i målet Bosio and Moretti mot Italien (nr 36608/97)
Domstolens text
Information Note on the Court’s case-law 10
September 1999
Bosio and Moretti v. Italy - 36608/97
Judgment 6.9.1999 [Section II]
Article 6
Civil proceedings
Article 6-1
Reasonable time
Length of civil proceedings: violation
The case concerns the length of civil proceedings brought against the applicants in April 1986. In April 1998 the parties reached a settlement which brought the proceedings to an end.
Law: The Court recalled that it had found in four judgments of 28 July 1999 that there existed in Italy a practice contrary to the Convention, resulting from an accumulation of breaches of the "reasonable time" requirement. It concluded that the length of the proceedings in this case (over 12 years) did not comply with that requirement and constituted a further example of the aforementioned practice.
Conclusion: violation (unanimous).
Article 41: The Court awarded each of the applicants 25 million lire (ITL) for non-pecuniary damage. It also awarded the two applicants 8 million lire for costs and expenses.
© Council of Europe/European Court of Human Rights
This summary by the Registry does not bind the Court.
Click here for the Case-Law Information Notes
Målets dokument (2)
- Dom, 6 september 1999 · engelska · länk
- Sammanfattning, 6 september 1999 (denna sida) · engelska